Center for Computing & Data Sciences – Construction Update – 9/24/21
During the weekend of September 25th On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. Also, on Saturday, crews will be on... More
Center for Computing & Data Sciences – Construction Update – 9/17/21
During the weekend of September 18th On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. Also on Saturday, crews will be on... More
Center for Computing & Data Sciences – Construction Update – 9/10/21
During the weekend of September 11 On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. Also on Saturday, crews will be on... More
Center for Computing & Data Sciences – Construction Update – 9/3/21
During the weekend of September 4 There will be no work on site Saturday or Sunday. During the week of September 6 In recognition of the Labor Day holiday, there will be no work on site Monday. Erection of the building’s structural steel frame will continue at the tower’s 15th and... More
Center for Computing & Data Sciences – Construction Update – 8/27/21
During the weekend of August 28th On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. Also on Saturday, crews will be on... More
Center for Computing & Data Sciences – Construction Update – 8/20/21
During the weekend of August 21 On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. On Sunday, from 7 am to 6... More
Center for Computing & Data Sciences – Construction Update – 8/13/21
During the weekend of August 14th On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. During the week of August 16th Erection of the... More
Center for Computing & Data Sciences – Construction Update – 8/6/21
During the weekend of August 7th On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. During the week of August 9th Erection of... More
Center for Computing & Data Sciences – Construction Update – 7/30/21
During the weekend of July 31st On Saturday, crews will be on site continuing to erect structural steel columns and beams. This work will occur in two shifts, first from 7 am to 3 pm and second from 3 pm to 10 pm. On Sunday, from 7 am to 11... More