New Balance Field Construction Activity for the Period of January 21 – January 26
Anticipated construction activities for the week of January 21 – January 26: **The contractor will be working on Saturday, 1/26/2013, beginning at 8:00am** 1. Site Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expected general construction noise... More
Fire Alarm Inspection 1/21/2013 – 1/25/2013
1/21/2013 Testing all rooms and common are from 7am - 3pm 37, 39, 141 Carlton St. 7, 19 Euston St. 1/22/2013 Testing all rooms and common area from 7am - 3pm 80, 82 Ivy St. 85, 87 St Mary's St. 985, 949 Commonwealth Ave 1/23/2013 Testing all rooms and common area from 7am - 3pm 37, 39, 41, More
Admissions Reception Center – Construction Activity 1/16/13
We have completed the work in the CAS Parking Lot, all of the earth mounds have been removed and the parking lot spaces have been re-striped. The lot is now open for use by all permit holders and deliveries as per normal. We thank you for your patience! We will... More
New Balance Field Construction Activity for the Period of January 14 – January 18
Anticipated construction activities for the week of January 14 – January 18: **The contractor will be working on Saturday, 1/12/2013, beginning at 8:00am** 1. Trucking of Demolition Debris and Soils: The contractor will continue hauling demolition debris off-site. They will also be excavating and hauling soils off-site. There will be... More
Fire Alarm Inspection 1/14/2013 – 1/18/2013
1/14/2013 Testing all rooms and comm. area from 8am - 3pm 514, 516, 518, 520, 522 Park Dr. 1/15/2013 Testing all rooms and comm. area from 8am - 3pm 515, 509, 500, 504 Park Dr. 1/16/2013 Testing all rooms and comm. area from 8am - 3pm 455, 457 Park Dr. 25, 27 Aberden St. 619 Memorial Dr. 1/17/2013... More
Admissions Reception Center – Construction Activity 1/7/13
Attached, please find a photo of the current conditions and our diagram for the work that has been completed as of Friday 1/4. We are now approximately 60% complete with the CAS Parking Lot portion and at this point we are on track for a Tuesday 1/15 completion with the... More
New Balance Field Construction Activity for the Period of January 7 – January 11
Anticipated construction activities for the week of January 7 – January 11: **The contractor will be working on Saturday, 1/5/2013, beginning at 8:00am doing advanced preparation for the demolition of 278 Babcock Street** 1. Building Demolition: The demolition of 278 Babcock will begin early in the week and is expected to be... More
Admissions Reception Center – Intersession Construction Activity
1) The CAS Parking Lot will be closed for vehicle access from Monday 12/24 through Monday 12/31. Two construction crews will be working full-time in the lot to install the new sewer separation lines with equipment trucks, excavated earth, back-hoes, etc., to take advantage of the University closing to complete... More
Fire Alarm Inspection 12/24/2012 – 12/28/2012
12/24/2012 Testing rooms only from 7am - 3pm 91 Bay State Rd from 6th floor to 8th fllor 140 Bay State Rd west side rooms 12/26/2012 Testing from 7am - 3pm 252, 254, 258, 264 Huntington Ave 1 University Rd. 115 Cummington St. 12/27/2012 Testing all common area and rooms from 7am - 3pm 17, 29, 31, 33, More
Power Outage 12/27/12 3-5 Cummington Street
On Thursday December 27, there will be intermittent electric power outages at 3-5 Cummington Street between the hours of 10:00AM to 12:00PM for NStar testing of high voltage equipment. There could be multiple outages within the 2 hour time frame which should last no longer than 10 minutes each. The... More