News
Kilachand Hall Phase 2 – Construction Update – 04/28/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Kilachand Hall Phase 2 – Construction Update – 04/21/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 04/21/23
Weekend of April 22nd There will be contractors working on the ceiling in the vicinity of the security desk and the surrounding lobby area. Week of April 17th Inside, sheetrock, acoustic ceiling tile grid, ductwork insulation, and flooring are being installed. The team will also be installing the acoustic ceiling tile grid... More
Kilachand Hall Phase 2 – Construction Update – 4/14/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 4/14/23
Project Updates The drywall installation in the Residence Life offices is expected to be completed this Saturday, 4/15. The electrical cabling above the ceiling is about 75% complete, and the HVAC ductwork installation is about 90% complete. The exterior concrete and brick wall removal at the new building entrance was... More
West Campus Dining Expansion – Construction Update – 4/7/23
Project Updates The contractor is nearing the completion of the sheetrock installation and the mechanical rough-in work. Sheetrock tapping has begun. The ACT ceilings in the egress corridor will be removed this Saturday, April 8th. Structural steel installation for the canopy has begun. Once done, the removal of the exterior concrete... More
Kilachand Hall Phase 2 – Construction Update – 4/7/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Kilachand Hall Phase 2 – Construction Update – 3/31/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 3/31/23
Project Updates Contractor began the installation of sheetrock following the rough-in inspection and sign off. Work on the overhead mechanical systems continued. The Sonotube placement for the footing of the new canopy was completed, along with the removal and block infill of an existing exterior door. Week of April 3rd Continuation... More
West Campus Dining Expansion – Construction Update – 03/24/23
Interior Work Last week, the electrical rough-in work was completed and inspected. The metal stud framing was also completed and is set to be inspected early next week, the week of March 27. Installation of drywall will begin once the inspection is passed. Installation of the HVAC ductwork will continue. Exterior Work ... More