Fire Alarm Inspection 9.8.2015 – 9.11.2015
9.8.2015 Testing all rooms and common area from 7am - 3pm 7, 11, 15, 17 Buswell St. 9.9.2015 Testing all rooms and common area from 7am - 3pm 29, 31, 33, 35, 37 Buswell St. 9.10.2015 Testing all rooms and common area from 7am - 3pm 39, 41, 43, 45, 47 Buswell St. 9.11.2015 Testing all... More
CILSE – Construction Activity – Week of August 30, 2015
For the week of August 30, 2015: The installation of the concrete foundation will continue next week. Heavy truck traffic will be entering and leaving the site during the course of the week. The project team’s primary focus is to provide a safe, reliable, well-marked, and consistent path of travel around the... More
Fire Alarm Inspection 8.24.2015 – 8.28.2015
8.24.2015 Testing all rooms and common areas 7am - 3pm 68-70, 74, 76, 78 Bay State Rd. 8.25.2015 Testing all rooms and common areas 7am - 3pm 80, 82, 86, 88, 90, 92 Bay State Rd. 8.26.2015 Testing all rooms and common areas 7am - 3pm 110, 112, 116, 118, 122, 128 Bay State Rd. 8.27.2015... More
CILSE – Construction Activity – Week of August 23, 2015
For the week of August 23, 2015: Installation of pressure-injected footings (PIFs) and piles is complete. Foundation work will continue throughout the week which will result in heavy truck traffic entering and leaving the site. Utility work on Commonwealth Avenue will continue next week which will cause Commonwealth Avenue to be... More
CILSE – Construction Activity – Week of August 17, 2015
For the week of August 17, 2015: Foundation form work, rebar, and concrete pouring will continue through next week. The contractor will begin trucking soil off site on Monday morning (8/17) starting at 6:00 AM. Concrete pouring will begin Tuesday afternoon (8/18). There will be deliveries of rebar and forms periodically... More
Nickerson Field Turf Time-lapse
New turf was installed at Nickerson Field in West Campus over the summer. Watch the field get a facelift in under a minute. More
CILSE – Construction Activity – Week of August 10, 2015
For the week of August 10, 2015: Pile driving operation will be completed next week. There will be a crane on site full time as of next week to support continued project operations. Work on the concrete foundation has begun. This will cause heavy truck traffic into the site throughout the week, More
CILSE – Construction Activity – Week of August 3, 2015
For the week of August 3, 2015: Installation of pressure-injected footings (PIFs) and piles will continue on Saturday (8/1) and throughout next week. Please note that work will be taking place on Saturdays through the end of July and into August. Forming and installation of rebar for pile caps will take place... More
Fire Alarm Inspection 8.3.2015 – 8.7.2015
8.3.2015 Testing all rooms and common area from 7am - 3pm 11-19, 53-57 Deerfield St. 533-541 Commonwealth Ave. 677-679 Beacon St. 8.4.2015 Testing all rooms and common area from 7am - 3pm 848, 850, 854, 856 Beacon St. 146 Commonwealth Ave. 8.5.2015 Testing all rooms and common area from 7am - 3pm 575, 580 Commonwealth Ave. 8.6.2015 Testing all... More
CILSE – Construction Activity – Week of July 27, 2015
For the week of July 27, 2015: Installation of pressure-injected footings (PIFs) and piles as well as underground utility work in the rear alley between 3-5 Cummington Mall and the College of Communication will continue on Saturday (7/25) and throughout next week. Please note that work will be taking place on... More