Category: Uncategorized
CILSE – Construction Activity – Week of November 1, 2015
This past week the project team completed the installation of the crawler crane. Structural steel installation will progress rapidly over the next few weeks.
CILSE – Construction Activity – Week of October 25, 2015
This past week the project team began installation of the large crawler crane. The crane installation will be completed on Saturday (10/24). Structural steel installation will progress rapidly over the next few weeks.
CILSE – Construction Activity – Week of October 18, 2015
This past week the project team implemented a new approach to the structural steel frame installation. A mid-sized hydraulic is being used to install steel on the east side of the site. The large crawler crane has been rescheduled to mobilize the end of next week.
CILSE – Construction Activity – Week of October 11, 2015
The project team is gearing up to start the installation of the building structural steel frame. We will continue to install the ground floor slab and will begin crane mobilization next week.
CILSE – Construction Activity – Week of October 4, 2015
The project team has completed the building foundation and will now start the ground floor slab. There will be large concrete slab pours on Tuesday (10/6), Thursday (10/8), Friday (10/9), and Saturday (10/10) next week.
CILSE – Construction Activity – Week of September 27, 2015
The installation of the concrete foundation will continue next week. The foundation work is approximately 85% complete and is expected to be finished in early October.
“Amazing” Law Tower Renovation Complete
Except for a few last-minute touches, the exterior and interior makeover of the Law Tower is now complete and right on schedule, rising in its fully restored glory beside the attached Sumner M. Redstone Building, which opened in 2014.
CILSE – Construction Activity – Week of September 20, 2015
For the week of September 20, 2015: The installation of the concrete foundation will continue next week. The foundation work […]
CILSE – Construction Activity – Week of September 13, 2015
For the week of September 13, 2015: The installation of the concrete foundation will continue next week. Heavy truck traffic […]
CILSE – Construction Activity – Week of September 6, 2015
For the week of September 6, 2015: The installation of the concrete foundation will continue next week. Heavy truck traffic […]