New Balance Field Construction Activity for the Period of May 6 – May 10
Anticipated construction activities for the week of May 6 – May 10: *The contractor WILL be working on Saturday, 5/4/2013. […]
Fire Alarm Inspection 5/6/2013 – 5/10/2013
QUIET HOURS 5/6/2013 Testing from 7am -3pm 11, 15, 19, 53, 55, 57 Deerfield St. 648, 650, 654, 656, 677 […]
Fire Alarm Inspection 4/29/2013 – 5/3/2013
4/29/2013 Testing rooms from 4th fl – 11th fl from 7am – 7pm 700 Commonwealth Ave Tower A, B and […]
Engineering Product Innovation Center Construction Activity for the Period of April 29 – May 3
Anticipated construction activities for the week of April 29 – May 3: 1. Site Work – The contractor will be […]
New Balance Field Construction Activity for the Period of April 29 – May 4
Anticipated construction activities for the week of April 29 – May 4: *The contractor will not be working on Saturday, […]
BWSC Sewerage Improvements On Beacon Street
Boston Water and Sewer Commission (BWSC) will be making improvements to the sewer system on Beacon Street. Construction will commence […]
Boston University Fitness and Wellness Center @ BCYF Blackstone Now Open
BU is doing its part to combat childhood obesity, which has more than tripled in the past 30 years, according […]
Sumner M. Redstone Building Groundbreaking Set for April 19
Celebration will mark official start of long-awaited construction project for School of Law Boston University School of Law will hold […]
Fire Alarm Inspection 4/22/2013 – 4/26/2013
4/22/2013 Testing all rooms and comm. area from 8am – 3pm 704, 708, 710, 714, 718, 722, 726, 728 Commonwealth […]
Engineering Product Innovation Center Construction Activity for the Period of April 15 – April 19
Anticipated construction activities for the week of April 15 – April 19: 1. Site Work – The contractor has completed […]