CILSE – Construction Activity – Week of 2/21/16
The project team will be prepping the structural steel for deck concrete pours on the west sides of the 8th and 9th floors as well as the roof. We have concrete pours scheduled every day next week.
CILSE – Construction Activity – Week of 2/7/16
Next week the project team will be prepping the structural steel for deck concrete pours on the west sides of the 7th, 8th, and, 9th floors as well as the roof. We have scheduled concrete pours for the west sides of the 7th and 8th floors, the roof, curbs, and pads.
CILSE – Construction Activity – Week of 1/25/16
During the week of January 25th, the project team will be preparing structural steel for concrete pours and continuing slab-on-deck concrete.
Dorm Lighting Upgraded Over Intersession
As part of BU’s plan to reduce energy consumption by 10% by July 2017, LED desk lamps were added over intersession to all rooms in West Campus, Warren Towers, and 1019 Comm Ave.
University Commits $50 Million for CFA
Over the next few years, BU’s Charles River Campus will see some invigorating changes along the stretch of Commonwealth Avenue that houses the College of Fine Arts.
CILSE – Construction Activity – Week of 1/17/16
Next week the project team will be finishing up structural steel and continuing slab-on-deck concrete. We have scheduled concrete pours Tuesday through Thursday (1/19 – 1/22) between the hours of 5 AM and 11 AM.
Fire Alarm Inspection 1.18.2016 – 1.22.2016
1.18.2016 Testing all units and common area from 7am -3pm 100, 120 Ashford St. 285, 300 Babcock St. 11 – […]
CILSE – Construction Activity – Week of 1/10/16
The project will be operational this weekend loading mechanical equipment to the roof on both Saturday (1/9) and Sunday (1/10).
Fire Alarm Inspection 12.21.2015 – 12.23.2015
12.21.2015 Testing all rooms from 7am – 3pm 273,275, 277 Babcock St. 12.22.2015 Testing all rooms from 7am – 3pm […]
CILSE – Construction Activity – Weeks of 12/21/15 – 1/8/2016
Over the next 3 weeks the project team will continue to erect structural steel. There will be 2 concrete pours per week while we complete structural steel.