Myles Standish Hall – Construction Activity – 6/10/17 – 6/16/17
The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed.
Fire Alarm Inspection – 6/6/2017-6/11/2017 (After Hours)
After Hours Buildings 6/6/2017 – Testing from 5 a.m.- 7 a.m. 928 Commonwealth Ave 6/7/2017 – Testing from 5 a.m.- […]
Myles Standish Hall – Saturday Work – 06/10/17
Saturday work at Myles Standish Hall will include demolition and steel installation in the Annex, installation of roof insulation, installation of masonry staging (Bay State Road), clean up and loadout (Bay State Road), and fire alarm testing.
Myles Standish Hall – Construction Activity – 6/3/17-6/9/17
The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed.
Joan and Edgar Booth Theatre & Boston University Production Center – Construction Activity – 6/1/17 – 6/19/17
Permitted by the Town of Brookline and in accordance with the approved Construction Management Plan, authorized work hours are 7 a.m. to 7 p.m. on weekdays, and Saturdays from 8:30 a.m. to 6 p.m. Sunday work schedules must be requested and approved by the Town.
Myles Standish Hall – Saturday Work – 06/03/17
Saturday work will include installation of valance units (floors 2-9), roof insulation, installation of masonry staging (Bay State Road), and clean up and loadout (Bay State Road).
Myles Standish Hall – Construction Activity – 5/27/17 – 6/2/17
Monday – 5/29/17 – No work. Site is closed for Memorial Day.
BU’s 2017 Commencement in a Flash
Time-lapse video records the setting up and tearing down of this year’s Commencement set up. Watch the setup, celebration, and breakdown of BU’s 144th Commencement on Nickerson Field Sunday, May 21
Myles Standish Hall – Saturday Work – 05/27/17
Saturday work will include installation of valance units, roof insulation, installation of masonry staging, waterproofing & curtainwall install on fraco, and clean up and loadout.
Myles Standish Hall – Construction Activity – 5/20/17 – 5/26/17
The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed. The work is expected to continue intermittently throughout the week.