CFA Renovations – Construction Update – 12/20/19
During December 20th – January 3rd: (Please note that there is work scheduled for Saturday, December 21st and Sunday, December […]
CFA Renovations – Construction Update – 10/18/19
During October 18th – October 25th: (Please note that there is work scheduled for Saturday, October 19th): General: Temporary signs […]
Geothermal Well Drilling Initiative – Construction Update – 10/18/19
During the week of October 21st: Parking Lot N The drilling subcontractor will continue drilling at GT-6 and setting the […]
Howard Thurman Center – Construction Update – 10/18/19
During the week of October 21: General: Temporary signage is posted to help the public navigate through the first floor. […]
Goldman School of Dental Medicine – Construction Update – 10/18/19
During the weekend of October 19: On Saturday, work will continue throughout the interior of the seven-story west addition and […]
Goldman School of Dental Medicine – Construction Update – 10/11/19
During the weekend of October 12: On Saturday, work will continue throughout the interior of the seven-story west addition and […]
Geothermal Well Drilling Initiative – Construction Update – 10/11/19
During the week of October 14th: Parking Lot N On Monday, 10/14, the drilling subcontractor will continue installing steel pipe […]
CFA Renovations – Construction Update – 10/11/19
During October 11th – October 18th: (Please note that there is work scheduled for Saturday, October 12th) General: Temporary signs […]
Howard Thurman Center – Construction Update – 10/10/19
During the week of October 14: General Temporary signage is posted to help the public navigate through the first floor. […]
Howard Thurman Center – Construction Update – 10/04/19
During the week of October 7: General: Temporary signage is posted to help the public navigate through the first floor. […]