Warren Towers Renovation Construction Update – 11/21/2025
General Project Information
- Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
- The team is currently in the main renovation phase of the project.
- Emergency Contacts:
- Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
- Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758
During the Weekend of 11/21
Saturday (1st Shift)
No work planned for Sunday
Exterior Work – Tower A
4th Floor Podium Roofs
- Low roofs will be used as laydown areas for tools, supplies, and materials.
- Crews will remove unnecessary tools, supplies, and equipment from the lower roofs via crane in preparation for winter.
East & West Facades
- Masons will continue with exterior brick veneer restoration, selective demolition, and installation of restoration anchors, air- and water-resistive barriers, new lintels, flashings, and relieving angles.

Front Façade and Commonwealth Ave.
- Masons will continue exterior restoration work and selective demolition.
- Crews will continue steel stud framing of window openings and exterior walls.
Rear Façade and Back Alley
- Masons will continue exterior restoration, selective demolition, and installation of anchors, barriers, and flashing systems.
Upper Roof
- Work continues on the construction of the new mechanical penthouse.
- Iron workers continue assembling steel beams and grating at the rooftop mechanical platform and roof screen supports.

West Podium Terrace
- Crews will continue working on the parapet walls.
- Installation of the new roofing system will continue.

Multipurpose Room Roof
- Crews will continue constructing the new boiler room.
- Installation of the new roofing system will continue.
Cummington Mall
(In and around the fenced area)
- Daily deliveries of tools, supplies, and materials will be received at the construction loading docks.
- The two-car personnel and materials hoist will remain in operation (with safety checks performed each morning at 6:00 a.m.).
Cummington Mall West
- Daily deliveries and dumpster loading will continue.
- BUPD detail officers and construction staff will assist with pedestrian and vehicular traffic.
Hinsdale Mall
- A crane will be in place on Saturday (1st shift) to hoist materials from the lower roofs.

- The Warren Towers parking garage (Lot K) entrances, exits, and bike storage room will always remain open.
- BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.
Interior Work – Tower A
-
- Demolition is ongoing, with debris loaded into hampers, transported, and emptied into dumpsters at the construction loading dock.
- Survey crews will continue layout and benchmarking.
- Steel stud framing and window installation will continue.
- Plaster patching at columns and beams continues.
- Modernization of the Tower A elevators by Otis Elevator Company continues
- Installation of structural steel clips, plates, kickers, and beam penetrations is ongoing.
- Sprinkler, HVAC, electrical, plumbing, and sheet metal ductwork installation will continue.

-
- Pressure testing of mechanical systems will continue.
- Fireproofing, spray foam, and firestopping will continue.
- Third-party inspectors remain onsite weekly for quality control and assurance.


Parking Garage
- Electricians will continue running wiring and conduits on all levels.
- Plumbers will continue installing new water and drain lines on all levels.
- Concrete and steel structural repair work will continue.
- Sprinkler installation will continue across all levels.
- Masons will continue installing block walls in the new mechanical and electric rooms.

- Please watch for adjusted parking patterns, cones, and observe signage.
During the Week of 11/24/2025
Crews will be working 1st, 2nd, and 3rd shifts
No work is planned on Thursday 11/27 (Thanksgiving)
Exterior Work – Tower A
4th Floor Podium Roofs
- Low roofs will continue to serve as laydown areas.
East & West Facades
- Crews will continue work on the low roofs east and west of Tower A.
- Masonry restoration and installation of façade components will continue.
- Installation of new windows and metal panels will continue.

Front Façade and Commonwealth Ave.
- Masons will continue restoration and selective demolition.
- Crews will continue steel stud framing of window openings and exterior walls.
Rear Façade and Back Alley
- Masons will continue exterior restoration and selective demolition.
Upper Roof
- Work on the new mechanical penthouse will continue.
- Iron workers will continue assembling steel beams and grating at the rooftop mechanical platform.

West Podium Terrace
- Work at the parapet walls will continue.
- Installation of the new roofing system will continue.
Multipurpose Room Roof
- Crews will continue constructing the new boiler room.
- Prefabricated mechanical equipment will be loaded into the west boiler room during the 2nd shift.
- Temporary lighting will be used for 2nd shift and will turn off at 11:00 p.m.
- Installation of the new roofing system will continue.
Cummington Mall
(In and around the fenced area)
- Daily deliveries of tools and materials will continue.
- The two-car hoist will remain in operation with daily safety checks. (The elevator operators begin their safety checks/preventative maintenance on the hoist way daily at 6:00 AM).
Cummington Mall West
- Daily deliveries and debris removal will continue.
- BUPD officers and construction staff will assist with traffic.
Hinsdale Mall
- The loading dock will be open for normal operations.
- The Warren Towers Parking Garage (Lot K) entrances, exits, and Bike Storage Room will always remain open.
- BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.
Interior Work
Dining Hall
- Crews will address water intrusion and above-ceiling work during 3rd shift hours.
Tower A
- Demolition is ongoing, with debris loaded into hampers, transported, and emptied into dumpsters at the construction loading dock.
- Survey crews will continue layout and benchmarking.
- Steel stud framing and window installation will continue.
- Plaster patching at columns and beams continues.
- Modernization of the Tower A elevators by Otis Elevator Company continues
- Installation of structural steel clips, plates, kickers, and beam penetrations is ongoing.
- Sprinkler, HVAC, electrical, plumbing, and sheet metal ductwork installation will continue.
- Pressure testing of mechanical systems will continue.
- Fireproofing, spray foam, and firestopping will continue.

- Third-party inspectors remain onsite weekly for quality control and assurance.
Parking Garage
- Work will continue in the main electrical room.
- Electricians will continue running wiring and installing conduits throughout the parking garage on the 1st, 2nd, and 3rd levels.
- Installation and assembly of the new electric switchgear for Tower A is ongoing.

- Plumbers are installing new water and drain lines in the basement and on the 1st, 2nd, and 3rd levels.
- Installation of mechanical piping continues.
- Construction of the new Parking & Transportation office on the first floor is ongoing.

- Installation of the new suspended electrical duct bank in the basement level is underway.


- Construction of the new fuel storage room in the southeast basement level is ongoing.
- Structural shoring is being installed at the basement ramp to support the delivery and loading of heavy electrical equipment.

- Concrete and steel structural repair work continues on the 1st, 2nd, and 3rd floors of the garage.

- Sprinkler installation will continue on all levels.
- Masons are installing block walls in the new mechanical and electric rooms.
- Installation of Tower A’s new electrical bus duct riser is ongoing.
- Please watch for adjusted parking patterns, BUPD detail officers, cones, and posted signage.
Future/Notable Tasks
- Adjustment of the fence line on Cummington Mall during winter intersession.
- Crane operations for installation of mechanical platform roof steel.
- Delivery and installation of main electric room switchgear on 11/29.
- Delivery and installation of 480V substation and paralleling gear on 12/5–12/6.
- Delivery and installation of windows on levels 5 and 6.
- Completion of 3rd section window leak testing.
- FM Global roof uplift testing to begin in December.
- Assembly of Tower B hoist way in December.
- Installation of rooftop HVAC equipment and emergency generator on Tower A.