Warren Towers Renovation Construction Update – 9/5/2025

General Project Information

  • The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11:00 pm, and the third shift starting at 11:00 pm and ending at 7:00 am. Weekend shifts will start at 7:00 am and end at 5:00 pm.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 9/6

No work planned to take place Sunday 9/7

Exterior Work- Tower A

4th-Floor Podium Roofs

  • Crews will use the low roofs as a laydown area for tools, supplies and materials.

East and West Façades

  • Crews will work on the low roofs, east and west of Tower A.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
  • Crews will also be adding steel stud framing and sheeting on the exterior walls.

Front Façade and on Commonwealth Avenue

  • The abatement demolition work is nearing completion.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Rear Façade and Back Alley

  • The abatement demolition work is nearing completion.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Upper Roof

  • Crews will demolish the exterior abatement of the elevator machine room headhouse.
  • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
  • Crews will continue assembling the new parapet.
Pictured is the wood blocking at the parapet of Tower A.

      West Podium and Terrace Roofs

      • Crews will continue installing temporary roofing membrane.
      • Crews will begin installing a topping slab.

      Multipurpose Room Roof 

      • Crews will continue constructing the new boiler room.
      • Masons will continue constructing the new parapet

      Cummington Mall
      (In and around the fenced area)

      • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
      • The 2-car personnel and materials hoist way operations are underway.

          Hinsdale Mall

          • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.
          Pictured is the crane work on Hinsdale Mall.

                  Interior Work

                  Tower A

                  • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                  • Abatement is nearing completion, the 2nd shift has ended, and the crew size has been decreased; remining team members are loading debris into trailers located in the construction loading dock.
                  • Crews will continue grinding the floor slab.
                  • Survey crews are working on setting up benchmarks and lay out points on each floor.
                  • Crews will continue cutting the concrete slab edge at every window opening.
                  • Crews will continue the interior framing of window openings and interior partitions and soffits on levels 15 through 18.
                  Pictured is the layout of the interior partition.
                  • Crews will be installing fire protection, sprinkler risers, and mains.
                  • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                  Pictured is the new piping for the HVAC work.
                  • Crews will continue conducting rough plumbing work
                  • Crews will continue installing structural steel reinforcements, plates, kickers, and beam penetrations.
                  • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                  • Crews will install windows on levels 15 through 18.

                                    Parking Garage

                                    • Electricians will continue running wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                    • Plumbers will install new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                    • Crews will construct the new fuel storage room in the southeast basement level of the parking garage.
                                    • Crews will continue concrete and steel structural repair work in the parking garage, 1st, 2nd, and 3rd floors.
                                    Pictured is the newly replaced floor slab.
                                    • Crews will continue sprinkler work on levels. Please observe signage and watch for adjusted parking patterns, cones.

                                      During the Week of 9/8

                                      Exterior Work- Tower A

                                      4th-Floor Podium Roofs

                                      • Crews will use the low roofs as a laydown area for tools, supplies and materials.

                                      East and West Façades

                                      • Crews will work on the low roofs, east and west of Tower A.
                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
                                      • Crews will also be adding steel stud framing and sheeting on the exterior walls.

                                      Front Façade and on Commonwealth Avenue

                                      • Abatement demolition is nearing completion.
                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                                      Rear Façade and Back Alley

                                      • Abatement demolition is nearing completion.
                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                                      Upper Roof

                                      • Crews will demolish the exterior abatement of the elevator machine room headhouse.
                                      • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
                                      Pictured is the steel for the Tower A mechanical penthouse.
                                      • Crews will continue assembling the new parapet.

                                          West Podium and Terrace Roofs

                                          • Crews will continue installing temporary roofing membrane.
                                          • Crews will continue installing a topping slab.

                                          Multipurpose Room Roof

                                          • Crews will continue installing the new boiler room and parapet.
                                          • Crews will continue installing AVB on the exterior.

                                            Cummington Mall
                                            (In and around the fenced area)

                                            • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
                                            • The 2-car personnel and materials hoist way operations are underway.

                                                Hinsdale Mall

                                                • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.

                                                Commonwealth Avenue

                                                • Crews from Brand Safway will continue installing staging on the sidewalk shed.
                                                • Crews will complete reinstalling the retail sign.
                                                Pictured is the retail sign.
                                                • Crews from Flett are working in front of the building on excavating and installing new utilities during the 3rd shift, as required by the city.
                                                • Road plates are being removed and restored during every shift. A BPD detail is onsite for vehicle and pedestrian traffic.

                                                  Interior Work

                                                  Tower A

                                                  • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                                                  • Abatement is nearing completion, the 2nd shift has ended, and crew sizes have been decreased; remaining crew members will be loading debris into trailers located in the construction loading dock.
                                                  • Crews will continue grinding the floor slab.
                                                  • Crews will continue conducting masonry wall patching and plastering.
                                                  • Survey crews are working on setting up benchmarks and lay out points on each floor.
                                                  • Crews will continue cutting the concrete slab edge at every window opening.
                                                  • Crews will continue the interior framing of window openings, interior partitions, and soffits on levels 15 through 18.  
                                                  • Crews will be installing fire protection, sprinkler risers, and mains.
                                                  • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                                                  Pictured is the new plumbing.
                                                  • Crews will continue the installation of structural steel clips, plates, kickers and beam penetrations.
                                                  • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                                                  • Crews will be installing windows on levels 15-18.
                                                  • Crews will be installing fuel oil piping in the former incinerator shaft.
                                                  Pictured is the new fuel oil piping.

                                                                Parking Garage

                                                                • The temporary bike storage room is open for use.
                                                                Pictured is the temporary bike storage room.
                                                                • Electricians will be running temporary power wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                                                Pictured are the electrical conduits.
                                                                • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                                                • Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
                                                                • Crews will continue conducting miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
                                                                Pictured is the floor prepared for concrete placement.
                                                                • Crews will continue conducting sprinkler work on all levels.
                                                                • Masons will be setting concrete blocks and constructing new electrical and mechanical rooms.
                                                                Pictured are the masons setting up to build a new electrical room.
                                                                • Please watch for adjusted parking patterns, cones and observe site signage.
                                                                • For the most updated information on the parking garage, click here.

                                                                    Off Site 

                                                                    • Crews are building detailed interior mockups of bathrooms and student rooms to work through each step for schedule efficiencies and constructability.

                                                                    Future/Notable Tasks

                                                                    • The large new fuel oil storage tanks will be delivered and placed, which will supply diesel to the new generators.
                                                                    • New topping slab will be placed at the West Terrace.
                                                                    • New electrical duct banks will be installed in the basement level.
                                                                    • Crews will begin constructing the new Parking and Transportation offices.
                                                                    • The windows will be tested for air and water infiltration.
                                                                    • Metal panel window trim will be installed.
                                                                    • Crews will conduct reoccurring crane work on Cummington Mall and Hinsdale Mall in the coming weeks.