Kilachand Hall Phase 2 – Construction Update – 9/23/22

General Project Information
- Daily Work Hours from 7 am-3:30 pm.
- The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place.
- Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road).
- Jersey barrier site containment in place, pedestrian walkway also in place and operational. The city sidewalk in front of Kilachand Hall is permitted to be used as part of the construction site limits.
- The bike lane in front of the building is fully functional.
- Additional meters have been purchased by the project to be used for resident parking for the duration of construction. The additional spots are on Deerfield Street at the intersection with Bay State Road and are available for use now.
BU parking spots directly behind Kilachand Hall on Back Street remain a no-parking zone. This will continue for the duration of the project to maintain an adequate drive lane for local traffic on Back Street and allow for the construction team to safely contain a work area north of the dormitory.
Top: Concrete block stair shaft at level 4
Left: New cast stone at restored building corners
Right: Waterproofing at corner restoration
During the weekend of September 24h
No work is scheduled over the weekend.
During the week of September 26th
- Riggs masonry to continue with new brick window headers at north elevation, until complete. Lintels and waterproofing complete at all windows except level 8 which is unoccupied. Continuing with building corner re-build, pouring column enclosures around the building.
- Crew continues with Concrete block construction of elevator hoist way and stair shaft, moving up through the 4th and 5th floors.
- SOS and Costello to continue with demo and clean up of level 9 decking.
- Mass Acoustics to continue framing in isolated renovation areas on each floor. Layout on level 9 to get under way.
- Murphy electric performing overhead rough-in renovation areas.
- Royal Steam completing startup of temporary exhaust fans on level 8.
- Riggs Contracting has carpenters onsite working on temporary protections throughout 9th floor.
Consigli/Riggs team on site cleaning support and supervision.
Please be aware of all directional signage, as pedestrian travel paths may be altered. We will continue to provide up-to-date information via these notifications.