Myles Standish Hall – Construction Update – 5/23/18
For 5/26/18 to 6/1/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
On-site Construction
Saturday Work – 5/26/18 – 7 am to 5 pm
- Clean up and load out
- Interior work – Myles
- Annex interior demo and load out
No work Monday, 5/28/18 due to Memorial Day
Myles – 7 am to 6 pm
Demolition / Load Out
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps
Masonry Restoration (Exterior – Bay State Road & Beacon Street)
- Continue with masonry restoration and demo at Beacon and Bay State Road
- Restoration of façade at hoist location
Roof (Exterior)
- MEP insulation
Site
- Myles
- Demo sidewalks and start underground
- Point Park
- Start installation of pavers and landscape
- Charlesgate
- Continue with Charlesgate bump out construction
Annex – 7 am to 6 pm
Demolition / Load Out
- Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps
Roof
- Masonry restoration
- Roof removal and re-installation
Masonry Restoration
- Beacon Street & Raleigh Street – Start façade restoratio