Myles Standish Hall – Construction Update – 5/23/18

Myles Standish Hall - Construction Update - 5/23/18 Myles Standish Hall - Construction Update - 5/23/18
For 5/26/18 to 6/1/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

Saturday Work – 5/26/18 – 7 am to 5 pm

  • Clean up and load out
  • Interior work – Myles
  • Annex interior demo and load out

No work Monday, 5/28/18 due to Memorial Day

Myles – 7 am to 6 pm

Demolition / Load Out

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps


Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demo at Beacon and Bay State Road
  • Restoration of façade at hoist location


Roof (Exterior)

  •  MEP insulation

Site

  • Myles
    • Demo sidewalks and start underground
  •  Point Park
    • Start installation of pavers and landscape
  • Charlesgate
    • Continue with Charlesgate bump out construction

Annex – 7 am to 6 pm

Demolition / Load Out

  • Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps

 Roof

  • Masonry restoration
  • Roof removal and re-installation

 Masonry Restoration

  • Beacon Street & Raleigh Street – Start façade restoratio