Myles Standish Hall – Construction Activity – 6/10/17 – 6/16/17

Myles Standish Hall - Construction Activity - 6/10/17 - 6/16/17

For 6/10/17 to 6/16/17:

Deliveries Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 6/10/17

  • Install insulation on roof and in basement
  • Install window caulking – Lift 8, Beacon Street
  • Clean up and loadout – Bay State Road
  • Annex interior demolition and loadout – Bay State Road
  • Fire alarm testing

 Verizon Off-Hours Work 6/11/17 to 6/15/17 

  • Verizon has informed us that they will be working on site from 7:00 p.m. to 6:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.

Fire Alarm Testing 6/10/17 to 6/16/17

  • The electrician will continue running a test of the fire alarm system on the construction-side of Myles. During this time, the strobe lights will be going off and minimal sound will be emitted through the speakers as needed. The work is expected to continue intermittently throughout the week. Please do not contact the Boston Fire Department during the testing. BFD will be notified in the event of an emergency.

Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue masonry restoration – Bay State Road & Beacon Street
  • Continue installation of staging and fraco – Bay State Road, Beacon Street, & the Point

Annex

  • Window removal
  • Load out of demolition debris – Bay State Road
  • Demolition on roof
  • Masonry restoration – Annex alley
  • Basement excavation
  • Site deliveries – Bay State Road

Roof Myles (Exterior)

  • Continue with roof demolition

Site Utility Work

  • Utility cut and cap work – Beacon Street