Myles Standish Hall – Construction Activity – 8/6/16 – 8/12/16

Deliveries

  • Subcontractors will receive deliveries all week between 7 a.m. and 5 p.m. on both Beacon Street and Bay State Road.

 

Onsite Construction

Saturday Work – 8/6/16

  • Permission and permitting have been secured from the City to work from 7 a.m. to 4 p.m.
  • Interior cleaning of Myles and the Annex and load out of all floors.
  • Load out of dumpsters on the Beacon Street side of building. Dumpsters will be swapped throughout the day.
  • Activities will require workers to be on the roof and trucks and equipment in point park area.

 

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Continue with load out down chute (interior).
  • Demolition and load out of basement.
  • Abatement on floors 1 and 2 (interior).
  • Demolition of floors 4, 5, and 6 (interior).

 

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue installation of concrete masonry units (CMU) at 9th floor on the Beacon Street side of building.
  • Continue with concrete repairs on the Beacon Street side of the building.
  • Continue with masonry façade demo on the Beacon Street side of the building.
  • Continue with masonry demo on swing above the Annex.
  • Continue installation of relieving angles on the Bay State Road side of the building.
  • Start rebuilding exterior façade on the Bay State Road side of the building.

 

Roof (Exterior)

  • Continue with layout and installation of CMU at parapet on the Bay State Road side of the building.
  • Coring and saw-cutting new holes and openings.
  • Temporary roofing of penetrations and parapet.

 

Alley Between Annex and Myles at Bay State Road

  • Form and pour slab on grade – Access from Bay State Road.
  • Site work – Continue with new sewer line to Annex. Trucks and equipment will be working at the corner of Raleigh Street and Bay State Road.
  • Alley – Complete grading, form and pour slab on grade, and install asphalt.

IMG_4382 IMG_4437