Myles Standish Hall – Construction Activity – 7/30/16 – 8/5/16
For 7/30/16 – 8/5/16
Deliveries
Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road
Onsite Construction
Saturday 07/30/16 – No work
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
- Continue with load out down chute (interior).
- Demolition and load out of basement.
- Abatement on floors 2, 3, and 4 (interior).
- Demolition of floors 5, 6, and 7 (interior).
Masonry Restoration (Exterior)
- Continue with masonry demo on the Bay State Road side of the building.
- Continue installation of concrete masonry units (CMU) at the 9th floor on the Beacon Street side of the building.
- Continue with concrete repairs on the Beacon Street and Bay State Road sides of building.
- Continue with masonry facade demo on the Beacon Street side of building at the 9th floor.
- Continue with masonry demo on swing above the Annex.
- Continue installation of relieving angles on the Bay State Road side of building.
Roof (Exterior)
- Continue with layout and installation of CMU at parapet on the Bay State Road side of the building.
- Coring and sawcutting new holes and openings.
- Temporary roofing of penetrations and parapet.
Alley Between Annex and Myles at Bay State Road
- Continue with forming for concrete at transformer pad.
- Waterproofing at transformer pad.
- Pour topping slab – Requires pump truck and concrete trucks at Bay State Road.
- Site work – Continue to bring drain line in off of Bay State Road and then into the alley.