Warren Towers Renovation Construction Update – 9/19/2025

General Project Information

  • The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11:00 pm, and the third shift starting at 11:00 pm and ending at 7:00 am. Weekend shifts will start at 7:00 am and end at 5:00 pm.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 9/20

Work planned to take place Saturday 9/20 during the 1st shift and Sunday 9/21 during the 3rd shift

Exterior Work- Tower A

4th-Floor Podium Roofs

  • Crews will use the low roofs as a laydown area for tools, supplies and materials.

East and West Façades

  • Crews will work on the low roofs, east and west of Tower A.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
  • Crews will also be adding steel stud framing and sheeting on the exterior walls.
  • Crews will be installing new windows on levels 15 through 18.  

Front Façade and on Commonwealth Avenue

  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Rear Façade and Back Alley

  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
  • Plumbers will be installing large overhead storm drain piping on the 1st floor of the alley on 3rd shift (Sunday– Thursday).

Upper Roof

  • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
  • Masons will be restoring the brick veneer on the existing north stair and elevator headhouse.
Pictured is work on the north stair and elevator headhouse.

      West Podium and Terrace Roofs

      • Crews will begin installing a topping slab.
      Pictured are the topping slab anchors.

      Multipurpose Room Roof 

      • Mechanical contractors will be installing piping in the new boiler room.

        Cummington Mall
        (In and around the fenced area)

        • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
        • The 2-car personnel and materials hoist way operations are underway.

        Cummington Mall West

        • Crews from Flett will be excavating and installing the new electrical service in the road on the 3rd Shift (Sunday – Thursday).

            Hinsdale Mall

            • Crews from Flett will be removing road plates, backfilling and paving on Saturday morning. 
            Pictured is the asphalt repaving area on Hinsdale Mall.
            • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.

                    Interior Work

                    Tower A

                    • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                    • Crews will continue grinding the floor slab.
                    • Survey crews are working on setting up benchmarks and lay out points on each floor.
                    • Crews will be working on the steel stud framing of the interior partitions and soffits on levels 15 through 18.
                    Pictured is the interior framing of a student room.
                    Pictured is the interior framing of a student room.
                    • Crews will continue patching the plaster.
                    • Crews will be installing fire protection, sprinkler risers, and mains.
                    • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                    Pictured is the rough plumbing for the student lounge sink.
                    • Crews will continue installing structural steel reinforcements, plates, kickers, and beam penetrations.
                    • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                    • Crews will install windows on levels 15 through 18.

                                      Parking Garage

                                      • Electricians will continue running wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                      • Plumbers will install new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                      • Crews will construct the new fuel storage room in the southeast basement level of the parking garage.
                                      • Crews will continue concrete and steel structural repair work in the parking garage, 1st, 2nd, and 3rd floors.
                                      Pictured is the concrete work in the parking garage.
                                      Pictured are the under-slab formwork and shoring.
                                      • Sprinkler work on level 3 will be ongoing.
                                      • Masons will be installing block walls in the new main electric room.
                                      Pictured is the new main electric room.
                                      • Please observe signage and watch for adjusted parking patterns, cones.

                                        During the Week of 9/22

                                        Exterior Work- Tower A

                                        4th-Floor Podium Roofs

                                        • Crews will use the low roofs as a laydown area for tools, supplies and materials.

                                        East and West Façades

                                        • Crews will work on the low roofs, east and west of Tower A.
                                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
                                        • Crews will also be adding steel stud framing and sheeting on the exterior walls.
                                        • Crews will be installing new windows on levels 15 through 18.  
                                        • There will be a window delivery for floors 12 through 14.

                                        Front Façade and on Commonwealth Avenue

                                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                                        Rear Façade and Back Alley

                                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
                                        • Plumbers will be installing large overhead storm drain piping on the 1st floor of the alley on 3rd shift. (Sunday – Thursday).
                                        Pictured is the storm drain piping.

                                        Upper Roof

                                        • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
                                        • Crews will be placing concrete for knee walks and the mechanical penthouse floor slab.
                                        • Mechanical contractors will be running new services up through the roof into the new Mechanical Penthouse.
                                        • Masonry crews will be restoring existing north stair and elevator headhouse brick veneer.

                                            West Podium and Terrace Roofs

                                            • Crews will be preparing to install the topping slab and parapet.
                                            Pictured is the preparation for the west terrace topping slab and parapet.

                                            Multipurpose Room Roof

                                            • Mechanical contractors will continue installing the new boiler room.

                                              Cummington Mall
                                              (In and around the fenced area)

                                              • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
                                              • The 2-car personnel and materials hoist way operations are underway.

                                              Cummington Mall West

                                              • Crews from Flett will be excavating and installing the new electrical service in the road on 3rd Shift (Sunday – Thursday).
                                              • There will be a crane in use on Tuesday morning to remove HVAC units from the West Terrace, for disposal. BUPD will be onsite to assist with pedestrian and vehicular traffic.
                                              Pictured is the crane plan for 9/23/25.

                                                  Hinsdale Mall

                                                  • A large crane will be set up in the street to hoist concrete to Tower A rooftop on Wednesday, 4:00 AM – 8:00PM.
                                                  Pictured is the Tower A penthouse concrete crane plan.
                                                  • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.

                                                      Interior Work

                                                      Tower A

                                                      • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                                                      • Crews will continue grinding the floor slab.
                                                      Pictured is ongoing floor grinding.
                                                      • Survey crews are working on setting up benchmarks and lay out points on each floor.
                                                      • Crews will be working on the steel stud framing of the interior partitions and soffits on levels 15 through 18.
                                                      • Crews will continue patching the plaster.
                                                      • Crews will be installing fire protection, sprinkler risers, and mains.
                                                      • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                                                      Pictured are the outside air risers.
                                                      • Crews will continue installing structural steel reinforcements, plates, kickers, and beam penetrations.
                                                      • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                                                      • Crews will install windows on levels 15 through 18.

                                                                        Parking Garage

                                                                        • Electricians will continue running wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                                                        Pictured are the new electrical conduits.
                                                                        • Plumbers will install new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                                                        • Crews will construct the new fuel storage room in the southeast basement level of the parking garage.
                                                                        • Crews will continue concrete and steel structural repair work in the parking garage, 1st, 2nd, and 3rd floors.
                                                                        • Sprinkler work on level 3 will be ongoing.
                                                                        • Masons will be installing block walls in the new main electric room.
                                                                        Pictured is the new main electrical room.
                                                                        • Please observe signage and watch for adjusted parking patterns, cones.

                                                                            Off Site 

                                                                            • Crews are building detailed interior mockups of bathrooms and student rooms to work through each step for schedule efficiencies and constructability.

                                                                            Future/Notable Tasks

                                                                            • There will be a delivery and placement on October 4th of the large new fuel oils storage tank which will supply diesel to the new generators.
                                                                            • New topping slab will be placed at the West Terrace on September 30th.
                                                                            • New electrical duct banks will be installed in the basement level.
                                                                            • Crews will begin constructing the new Parking and Transportation offices.
                                                                            • Metal panel window trim will be installed.
                                                                            • Crews will conduct reoccurring crane work on Cummington Mall and Hinsdale Mall in the coming weeks.
                                                                            • There will be handrail alterations in the north and south stairs of Tower A.

                                                                              View all posts