Warren Towers Renovation Construction Update – 9/12/2025

General Project Information

  • The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11:00 pm, and the third shift starting at 11:00 pm and ending at 7:00 am. Weekend shifts will start at 7:00 am and end at 5:00 pm.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 9/13

No work planned to take place Sunday 9/14

Exterior Work- Tower A

4th-Floor Podium Roofs

  • Crews will use the low roofs as a laydown area for tools, supplies and materials.

East and West Façades

  • Crews will work on the low roofs, east and west of Tower A.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
  • Crews will also be adding steel stud framing and sheeting on the exterior walls.
  • Crews will be installing new windows on levels 15 through 18.  
Pictured are the new exterior windows.

Front Façade and on Commonwealth Avenue

  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
Pictured is the view of Commonwealth Avenue.

Rear Façade and Back Alley

  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Upper Roof

  • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
Pictured is the construction of the Tower A mechanical penthouse.
  • Crews will continue assembling the new parapet.

      West Podium and Terrace Roofs

      • Crews will continue installing temporary roofing membrane.
      • Crews will begin installing a topping slab.

      Multipurpose Room Roof 

      • Crews will continue constructing the new boiler room.
      Pictured is the new west mechanical room.
      • Masons will continue constructing the new parapet.

      Cummington Mall
      (In and around the fenced area)

      • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
      • The 2-car personnel and materials hoist way operations are underway.

          Hinsdale Mall

          • The crews working the 3rd shift are continuing their underground utility work.   
          Pictured is the storm drain utility work on Hinsdale Mall.
          • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.

                  Interior Work

                  Tower A

                  • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                  • Abatement is nearing completion, the 2nd shift has ended, and the crew size has been decreased; remining team members are loading debris into trailers located in the construction loading dock.
                  • Crews will continue grinding the floor slab.
                  • Survey crews are working on setting up benchmarks and lay out points on each floor.
                  • Crews will continue cutting the concrete slab edge at every window opening.
                  • Crews will continue the interior framing of window openings and interior partitions and soffits on levels 10 through 18.
                  • Crews will continue patching the plaster.
                  • Crews will be installing fire protection, sprinkler risers, and mains.
                  Pictured is a new sprinkler riser.
                  • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                  Pictured is a typical wall and slab opening for the HVAC piping.
                  • Crews will continue conducting rough plumbing work.
                  • Crews will continue installing structural steel reinforcements, plates, kickers, and beam penetrations.
                  • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                  • Crews will install windows on levels 15 through 18.

                                    Parking Garage

                                    • Electricians will continue running wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                    • Plumbers will install new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                    • Crews will construct the new fuel storage room in the southeast basement level of the parking garage.
                                    • Crews will continue concrete and steel structural repair work in the parking garage, 1st, 2nd, and 3rd floors.
                                    Pictured is beam replacement work.
                                    • Masons will be installing block walls in the new main electric room.
                                    Pictured is the new main electric room.
                                    • Crews will continue sprinkler work on levels. Please observe signage and watch for adjusted parking patterns, cones.

                                      During the Week of 9/15

                                      Exterior Work- Tower A

                                      4th-Floor Podium Roofs

                                      • Crews will use the low roofs as a laydown area for tools, supplies and materials.

                                      East and West Façades

                                      • Crews will work on the low roofs, east and west of Tower A.
                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
                                      • Crews will also be adding steel stud framing and sheeting on the exterior walls.
                                      • Crews will be installing new windows on levels 15 through 18.  
                                      Pictured is the interior of the new windows.

                                      Front Façade and on Commonwealth Avenue

                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
                                      Pictured is the new brick veneer being replaced at the relieving angles.

                                      Rear Façade and Back Alley

                                      • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                                      Upper Roof

                                      • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.
                                      • Crews will continue assembling the new parapet.

                                          West Podium and Terrace Roofs

                                          • Crews will continue installing temporary roofing membrane.
                                          • Crews will continue installing a topping slab.

                                          Multipurpose Room Roof

                                          • Crews will continue installing the new boiler room and parapet.
                                          • Crews will continue installing the new parapet.

                                            Cummington Mall
                                            (In and around the fenced area)

                                            • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
                                            • The 2-car personnel and materials hoist way operations are underway.

                                                Hinsdale Mall

                                                • The loading dock has been reopened for deliveries and services. The east exit of the parking garage remains closed; however, the west exit will remain open.

                                                    Interior Work

                                                    Tower A

                                                    • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                                                    • Abatement is nearing completion, the 2nd shift has ended, and crew sizes have been decreased; remaining crew members will be loading debris into trailers located in the construction loading dock.
                                                    • Crews will continue grinding the floor slab.
                                                    • Crews will continue conducting masonry wall patching and plastering.
                                                    • Survey crews are working on setting up benchmarks and lay out points on each floor.
                                                    • Crews will continue cutting the concrete slab edge at every window opening.
                                                    Pictured are crew members sawing the slab.
                                                    • Crews will continue the interior framing of window openings, interior partitions, and soffits on levels 10 through 18.  
                                                    • Crews will continue patching the plaster.
                                                    • Crews will be installing fire protection, sprinkler risers, and mains.
                                                    • Crews will be conducting rough work on HVAC piping, plumbing, and ductwork.
                                                    Pictured is prefab HVAC piping.
                                                    • Crews will continue the installation of structural steel clips, plates, kickers and beam penetrations.
                                                    • Crews will continue applying spray fireproofing, expanding foam insulation, and firestopping.
                                                    • Crews will be installing windows on levels 15 through 18.

                                                                  Parking Garage

                                                                  • Electricians will be running temporary power wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                                                  • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                                                  • Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
                                                                  • Crews will continue conducting miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
                                                                  Pictured are the new steel beams and full-depth slab replacement.
                                                                  • Crews will continue conducting sprinkler work on level 3.
                                                                  • Masons will be setting concrete blocks and constructing new electrical and mechanical rooms.
                                                                  • Please watch for adjusted parking patterns, cones and observe site signage.
                                                                  • For the most updated information on the parking garage, click here.

                                                                      Off Site 

                                                                      • Crews are building detailed interior mockups of bathrooms and student rooms to work through each step for schedule efficiencies and constructability.

                                                                      Future/Notable Tasks

                                                                      • The large new fuel oil storage tanks will be delivered and placed, which will supply diesel to the new generators.
                                                                      Pictured is tan pad for the fuel oil storage.
                                                                      • New topping slab will be placed at the West Terrace.
                                                                      • New electrical duct banks will be installed in the basement level.
                                                                      • Crews will begin constructing the new Parking and Transportation offices.
                                                                      • The windows will be tested for air and water infiltration.
                                                                      • Metal panel window trim will be installed.
                                                                      • Crews will conduct reoccurring crane work on Cummington Mall and Hinsdale Mall in the coming weeks.
                                                                      • There will be window deliveries for levels 12 through 14 of Tower A.  
                                                                      • There will be handrail alterations in the north and south stairs of Tower A. 

                                                                          View all posts