Warren Towers Renovation Construction Update – 8/15/2025

General Project Information

  • The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11:00 pm, and the third shift starting at 11:00 pm and ending at 7:00 am. Weekend shifts will start at 7:00 am and end at 4:00 pm.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 8/16

No work planned to take place Sunday 8/17

Exterior Work- Tower A

4th-Floor Podium Roofs

  • Crews will use the low roofs as a laydown area for tools, supplies and materials.

East and West Façades

  • Crews will work on the low roofs, east and west of Tower A.
  • Crews will continue abatement demolition, working in a top-down sequence.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.
Pictured is a new relieving angle.

Front Façade and on Commonwealth Avenue

  • Crews will continue abatement demolition, working in a top-down sequence.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Rear Façade and Back Alley

  • Crews will continue installing overhead protection, staging, shoring, and stair components in the South Alley.
  • Crews will continue abatement demolition, working in a top-down sequence.
  • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

Upper Roof

  • Crews will be installing temporary roofing.
  • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.

      West Podium and Terrace Roofs

      • Crews will continue installing temporary roofing membrane.
      • Masons will begin constructing the new CMU parapet walls.

      Multipurpose Room Roof 

      • Crews will continue constructing the new boiler room.
      Pictured is the new boiler room.

      Cummington Mall
      (In and around the fenced area)

      • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
      • The 2-car personnel and materials hoist way operations are underway.
      • The team will participate in daily contractor meetings to review site safety, logistics, and the code of conduct.
      • Crews have pulled back the jersey barriers and fence line to open Cummington Mall to through traffic.
      Pictured is Cummington Mall, which has been reopened to through traffic.

          Hinsdale Mall

          • Crews will continue installing the new grease trap system, through the replacement of concrete sidewalks and bituminous pavement, and with backfilling.
          Pictured is the grease trap system.
          • The loading dock has been reopened for deliveries and services. The, east exit of the parking garage remains closed; however, the west exit will remain open.    

                Interior Work

                Tower A

                • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                • Abatement is ongoing; debris is loaded into trailers located in the construction loading dock.
                • Crews will continue grinding the floor slab.
                • Survey crews are working on setting up benchmarks and lay out points on each floor.
                • Crews will continue the interior framing of window openings on levels 15 through 18.  
                • Crews will continue cutting the concrete slab edge at every window opening.
                • Crews will continue installing structural steel reinforcement and beam penetrations.
                • Crews will continue working on the interior framing of window openings.
                • Crews will be conducting rough work on the sprinklers.
                • Crews will continue the installation of structural steel clips, plates, kickers and beam penetrations.

                        4th-Floor Podium Level
                        (Corridors, security areas, study areas, and the multipurpose room)

                        • Crews are completing the final drywall patching, painting, touchups, and cleaning.

                        Parking Garage

                        • Electricians will be running temporary power wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                        • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                        Pictured is the new plumbing in the parking garage.
                        • Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
                        • Crews will conduct miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
                        Pictured are new steel beams.
                        • Crews will continue sprinkler work on all levels.
                        • Please watch for adjusted parking patterns, cones and observe site signage.

                        Lobby 

                        • Crews will conduct ongoing electrical work within the new fire command center.

                        During the Week of 8/18

                        Exterior Work- Tower A

                        4th-Floor Podium Roofs

                        • Crews will use the low roofs as a laydown area for tools, supplies and materials.

                        East and West Façades

                        • Crews will work on the low roofs, east and west of Tower A.
                        • Crews will continue abatement demolition, working in a top-down sequence.
                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                        Front Façade and on Commonwealth Avenue

                        • Crews will continue abatement demolition, working in a top-down sequence.
                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                        Rear Façade and Back Alley

                        • Crews will continue installing overhead protection, staging, shoring, and stair components in the South Alley.
                        • Crews will continue abatement demolition, working in a top-down sequence.
                        • Masons will continue with their exterior brick veneer restoration work, selective demolition, installation of restoration anchors, new lintels, and relieving angles.

                        Upper Roof

                        • Crews will be installing temporary roofing.
                        Pictured is the temporary roofing of Tower A.
                        • Crews will continue installing steel stub columns and supports for the new penthouse and roof screening.

                            West Podium and Terrace Roofs

                            • Crews will continue installing temporary roofing membrane.
                            • Masons will begin constructing the new CMU parapet walls.

                            Multipurpose Room Roof

                            • Crews will continue installing the new boiler room.

                            Cummington Mall
                            (In and around the fenced area)

                            • There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
                            • The 2-car personnel and materials hoist way operations are underway.
                            • The team will participate in daily contractor meetings to review site safety, logistics, and the code of conduct.
                            • Crews have pulled back the jersey barriers and fence line to open Cummington Mall to through traffic.

                                Hinsdale Mall

                                • Crews will continue installing the new grease trap system, through the replacement of concrete sidewalks and bituminous pavement, and with backfilling.
                                • The loading dock has been reopened for deliveries and services. The, east exit of the parking garage remains closed; however, the west exit will remain open.    

                                    Interior Work

                                    Tower A

                                    • Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).
                                    • Abatement is ongoing; debris is loaded into trailers located in the construction loading dock.
                                    • Crews will continue grinding the floor slab.
                                    • Survey crews are working on setting up benchmarks and lay out points on each floor.
                                    • Crews will continue the interior framing of window openings on levels 15 through 18.  
                                    • Crews will continue cutting the concrete slab edge at every window opening.
                                    • Crews will continue installing structural steel reinforcement and beam penetrations.
                                    • Crews will continue working on the interior framing of window openings.
                                    Pictured is the new window framing.
                                    • Crews will be conducting rough work on the sprinklers.
                                    • Crews will continue the installation of structural steel clips, plates, kickers and beam penetrations.

                                          4th-Floor Podium Level
                                          (Corridors, security areas, study areas, and the multipurpose room)

                                          • Crews are completing the final drywall patching, painting, touchups, and cleaning.

                                          Parking Garage

                                          • Electricians will be running temporary power wiring and conduits throughout the parking garage, 1st, 2nd, and 3rd levels.
                                          Pictured are the electrical conduits in the parking garage.
                                          • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                                          • Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
                                          Pictured is the work in the new fuel storage block.
                                          • Crews will conduct miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
                                          Pictured is some of the concrete repair work.
                                          Pictured is the replacement of the concrete slab.
                                          • Crews will continue sprinkler work on all levels.
                                          • Please watch for adjusted parking patterns, cones and observe site signage.

                                          Lobby

                                          • Crews will conduct ongoing electrical work within the new fire command center.
                                          Pictured is the new fire command center.

                                          Off Site 

                                          • Crews are building detailed interior mockups of bathrooms and student rooms to work through each step for schedule efficiencies and constructability.
                                          Pictured is a restroom mockup.

                                          Future/Notable Tasks

                                          • Crews will conduct reoccurring crane work on Cummington Mall west in the coming weeks.
                                          • Crews will be reopening Hinsdale Mall.
                                          • Crews will begin framing the interior walls and soffits in Tower A.
                                          • Crews will begin rouch mechanical, electrical, plumbing and fire protection work in Tower A.
                                          • The first shipment of new exterior window units will be delivered to the site.
                                          • Crews will begin constructing the new Parking and Transportation offices.