Warren Towers Renovation Construction Update – 6/27/2025
General Project Information
- The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11:00 pm, and the third shift starting at 11:00 pm and ending at 7:00 am. Weekend shifts will start at 4:00 am and end at 10:00 pm; weekend hours have been extended to accommodate crane work.
- The team is currently in the main renovation phase of the project.
- Emergency Contacts:
- Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
- Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758
During the Weekend of 6/27
No work planned to take place Sunday 6/29; however, crane removal may extend from Saturday 6/28 into Sunday 6/29
Exterior Work- Tower A
East and West Façades
- Crews will work on the low roofs, east and west of Tower A.
- Crews will continue abatement demolition, working in a top-down sequence.

Front Façade and on Commonwealth Avenue
- Crews will continue abatement demolition, working in a top-down sequence.
- Masons will continue brick veneer restoration work, selective demolition, and installing restoration anchors.
Rear Façade and Back Alley
- Crews will continue installing overhead protection, staging, shoring, and stair components in the South Alley and on the basement and 1st-floor levels.
- Crews will continue abatement demolition, working in a top-down sequence.
- Masons will continue with brick veneer restoration work, selective demolition, and installing restoration anchors.
Upper Roof
- Crews will continue the abatement and demolition of the mechanical penthouse.
West Podium and Terrace Roofs
- Crews will continue abatement demolition on the west terrace. Crews will utilize a crane to hoist demolition debris down to dumpsters, which will be located on the west side of Cummington Mall.

Hinsdale Mall
- A crane will arrive in the early morning on Saturday 6/28, the crews will set it up, utilize it for lift work, and disassemble it the same day, which will require extended working hours on Saturday.
- Crews will use a large crane to lift and set up precast concrete tank structures into the recharge system excavation.
- A portion of Hinsdale Mall is now closed, including the loading dock and east exit of the parking garage. The west exit of the parking garage will remain open.
Towers B
- The crews working with Grande Masonry will finish the brick veneer opening on the south elevation, in order to progress with the staging tiebacks.

Interior Work
Tower A
- Crews will continue their make safe electrical, plumbing, and HVAC work on all floors.
- Crews will continue demolition work and will load debris into hampers and transport it to be emptied into dumpsters (located in the construction loading dock).


Dining Hall
- Temporary protections are in place.
- Crews are reworking and relocating the existing mechanical, electrical, plumbing, and fire protection systems.
- Crews have begun steel stud framing and installing structural steel.

4th-Floor Podium Level
(Corridors, security areas, study areas, and the multipurpose room)
- Temporary protections are in place.
- Crews are reworking and relocating the existing mechanical, electrical, plumbing, and fire protection systems, and installing new ones.
Parking Garage
- Electricians will be running temporary power wiring and conduits throughout the parking garage.
- HVAC teams will continue working in and around the temporary electric room on the first floor.
- Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
- Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
- The Existing Bike Storage room is demolished and has been closed. Crews are working on structural concrete repairs in this area.
- Crews will conduct miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
- Crews will continue sprinkler work on all levels.
- Crews will continue reinforcing structural steel work. Please watch for adjusted parking patterns, cones and observe site signage.
During the Week of 6/30
No on-site work is planned to take place Friday 7/4
Exterior Work- Tower A
4th-Floor Podium Roofs
(East and West Facades)
- Crews will use the low roofs as a laydown area for tools, supplies and materials.
East and West Façades
- Crews will work on the low roofs, east and west of Tower A.
- Crews will continue abatement demolition, working in a top-down sequence.
Front Façade and on Commonwealth Avenue
- Crews will continue abatement demolition, working in a top-down sequence.
- Masons will begin brick veneer restoration work, washdown, selective demolition, and installing restoration anchors.
Rear Façade
- Crews will continue abatement demolition, working in a top-down sequence.
- Masons will continue with brick veneer restoration work, washdown, selective demolition, and installing restoration anchors.
Upper Roof
- Crews will continue the abatement and demolition of the mechanical penthouse.
Exterior Work- Tower B
4th-Floor Podium Roofs
(East and West Facade)
- Crews will continue work on the low roofs, east and west of Tower B, installing the staging support steel.
Rear Facade
- Crews will work from swing staging to create openings in the brick veneer to install staging tie backs.
West Podium and Terrace Roofs
- Crews will continue abatement demolition on the west terrace. Crews will utilize a crane to hoist demolition debris down to dumpsters, which will be located on the west side of Cummington Mall.

Cummington Mall
(In and around the fenced area)
- There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
- The 2-car personnel and materials hoist way operations are underway.
- The team will participate in daily contractor meetings to review site safety, logistics, and the code of conduct.
- A portion of Cummington Mall is now closed. Please observe site signage and BUPD detail instructions.
- The Hub Foundations Co. will continue installing the Tower B hoist way and common tower foundation piles.
Hinsdale Mall
- Crews will continue phase 1 of the storm water retention system installation. A portion of Hinsdale Mall is now closed, including the loading dock and east exit of the parking garage. The west exit of the parking garage will remain open.
South Alley
- Crews will continue installing overhead protection, staging, shoring, and stair components in the south alley.
Interior Work
Tower A
- Crews will continue make safe electrical, HVAC, and plumbing work on all floors.

- Crews will continue with demolition. They will load debris into hampers to be transported and emptied into dumpsters (which are located in the construction loading dock).

Towers B
- Crews will begin the selective demolition at staging tie backs in student rooms.
Dining Hall
- Temporary protections are in place.
- Crews are reworking and relocating the existing mechanical, electrical, plumbing, and fire protection systems, and adding new systems.
4th-Floor Podium Level
(Corridors, security areas, study areas, and the multipurpose room)
- Temporary protections are in place.
- New construction access, a ramp, and an opening are in place on the south wall west of Tower B.
- Crews are reworking and relocating the existing mechanical, electrical, plumbing, and fire protection systems, and installing new ones.
Parking Garage
- Electricians will be running temporary power wiring and conduits throughout the parking garage.
- HVAC teams will continue working in and around the temporary electric room on the first floor.
- Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
- Crews will continue constructing the new fuel storage room in the Southeast basement level of the parking garage.
- The Existing Bike Storage room is demolished and has been closed. Crews are working on structural concrete repairs in this area.
- Crews will conduct miscellaneous concrete structural repairs on the 1st, 2nd, and 3rd levels of the parking garage.
- Crews will continue sprinkler work on all levels.
- Crews will continue reinforcing structural steel work. Please watch for adjusted parking patterns, cones and observe site signage.
Future/Notable Tasks
- Crews will conduct reoccurring crane work on Cummington Mall west in the coming weeks.