Warren Towers Renovation Construction Update – 5/23/2025
General Project Information
- The first weekday work shift will begin at 7:00 am and end at approximately 3:30 pm, with the second shift beginning at 3:00 pm and ending at 11 pm. Weekend shifts will start at 7:00 am and end at 4:00 pm.
- The team is currently in the main renovation phase of the project.
- Emergency Contacts:
- Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
- Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758
During the Weekend of 5/24
No work to take place Sunday 5/25, nor Monday 5/26
Exterior Work
- Crews will continue abatement demolition in the South Wall Quad rooms.
Interior Work
Tower A
- Crews will continue their make safe electrical, plumbing, and HVAC work.
- Crews will continue installing temporary lighting, power, and fire alarms (heat detectors).
During the Week of 5/26
Exterior Work- Tower A
4th-Floor Podium Roofs
(East and West Facades)
- Crews will remove stone ballasts from the roof level, using a vacuum truck. This truck will be set up in multiple locations. This will produce intermittent noise.

- Crews will continue installing temporary lighting on the staging levels.
- Crews will begin abatement demolition, starting in a top-down sequence.
- Masons will begin brick veneer restoration work, selective demolition, and working on restoration anchors.
Front Façade and on Commonwealth Avenue
- Crews will begin abatement demolition, starting in a top-down sequence.
- Masons will begin brick veneer restoration work, selective demolition, and working on restoration anchors.
- Crews will be installing a roof membrane on the overhead platform to minimize dripping.
Rear Façade and Back Alley
- Crews will continue installing overhead protection, staging, shoring, and stair components in the South Alley.

- Crews will begin abatement demolition, starting in a top-down sequence.
- Masons will begin brick veneer restoration work, selective demolition, and working on restoration anchors.
- Plumbers will continue installing temporary risers for roof drainage and the portable toilet vacuum waste line in the south staging.
Upper Roof
- Crews will continue the abatement and demolition of the parapets and mechanical penthouse.

Exterior Work- Tower B
4th-Floor Podium Roofs
(East and West Facade)
- Crews will begin installing the staging support steel east and west of Tower B.
Upper Roof
- Crews will begin setting up swing staging on the South elevation, in order for crews to install the necessary bridge tiebacks.
West Podium and Terrace Roofs
- Crews will begin abatement demolition west of Tower C. Crews will utilize a crane to hoist demolition debris down to dumpsters, which will be located on the west side of Cummington Mall.

Cummington Mall
(In and around the fenced area)
- There will be daily deliveries of tools, supplies, and materials to be received at the construction loading dock.
- The team will participate in daily contractor meetings to review site safety, logistics, and the code of conduct.
- A portion of Cummington Mall is now closed. Please observe site signage and BUPD detail instructions.

Hinsdale Mall
- Crews will begin Phase 1 of the new grease trap and storm water retention system excavation. This will close a portion of Hinsdale Mall and the east exit of the parking garage and the loading dock; however, the west exit will remain open.

Interior Work
Tower A
- Crews will begin make safe electrical, HVAC, and plumbing.

- Crews will install temporary lighting, power, and fire alarm (heat detectors).
- Crews will begin abatement demolition on all floors.
Towers B
- Crews will access the building with swing staging components up to the roof level.
Dining Hall
- Crews will install temporary protection in preparation for ceiling removal.
- Crews will remove ceilings from selected areas, in order to gain access for structural steel work.
- Crews will conduct enabling work at the skylight in preparation for its removal and replacement.
Parking Garage
- Electricians will be running temporary power wiring and conduits throughout the parking garage.
- HVAC teams will begin working in and around the temporary electric room on the first floor.
- Plumbers will install new water and drain lines in the basement level.
- Crews will begin demolition and excavation in the southeast basement level of the parking garage, in order to build a new fuel storage tank room.

- Crews will begin the demolition of the parking office on the first floor, in order to make room for the new bike storage area.
- The existing bike storage room will be closed, demolished, and converted into a new electrical switchgear room.
- Crews will conduct miscellaneous concrete structural repairs throughout all levels of the parking garage.
- Crews will begin first floor sprinkler work. Please watch for adjusted parking patterns, cones and observe site signage.
Future/Notable Tasks
- Crews will begin foundation work for Tower B hoist way.
- Crews will begin preparation work on Tower B installing structural tiebacks in student rooms (south wall).
- Third shift utility work will begin on Commonwealth Avenue.
- Crews will conduct reoccurring crane work on Cummington Mall west in the coming weeks.