West Campus Dining Expansion – Construction Update – 07/14/23

General Project Updates

  • This past week, excavation work on the new sidewalk was completed, and the site was prepped and ready for the curb and paver base layer.
  • Sheetrock wall installation is completed along with the first and second coats of paint in many areas.
  • Tapping of soffit faces has been completed.
  • Containment and abatement of room 122 has been completed.
  • Kitchen floor removal is complete. Electrical coring and rough-in for kitchen equipment are ongoing.
  • Lighting swap out is ongoing.
  • Roof exhaust and hood connections are complete.
  • Rear store front glass has been removed.

Week of July 17th

  • Shutdown of the electrical panel for the kitchen equipment and feed new wiring.
  • Start tile infill in the front of house equipment area.
  • Tile floor at the gluten-free walk-in fridge.
  • Power shutdown for relocation of generator enunciator.
  • Core holes, set, and tie-in for floor sinks.
  • Finish up wall taping and prepare for paint.
  • Set walkway curb. Pour base layer concrete for pavers. Curb and paver base work in the plaza/sidewalk area.
  • Core for the power unit of the turnstiles.