West Campus Dining Expansion – Construction Update – 07/14/23
General Project Updates
- This past week, excavation work on the new sidewalk was completed, and the site was prepped and ready for the curb and paver base layer.
- Sheetrock wall installation is completed along with the first and second coats of paint in many areas.
- Tapping of soffit faces has been completed.
- Containment and abatement of room 122 has been completed.
- Kitchen floor removal is complete. Electrical coring and rough-in for kitchen equipment are ongoing.
- Lighting swap out is ongoing.
- Roof exhaust and hood connections are complete.
- Rear store front glass has been removed.
Week of July 17th
- Shutdown of the electrical panel for the kitchen equipment and feed new wiring.
- Start tile infill in the front of house equipment area.
- Tile floor at the gluten-free walk-in fridge.
- Power shutdown for relocation of generator enunciator.
- Core holes, set, and tie-in for floor sinks.
- Finish up wall taping and prepare for paint.
- Set walkway curb. Pour base layer concrete for pavers. Curb and paver base work in the plaza/sidewalk area.
- Core for the power unit of the turnstiles.