West Campus Dining Expansion – Construction Update – 07/07/23

General Project Updates

  • This past week, exterior work began and excavation of the site’s utilities and stockpiling soil took place.
  • Soffit framing and drywall installation continued. The framing inspection was approved Wednesday.
  • Electrical installation was completed and the old lights were swapped out.
  • The KDP and KP3 panels were shut down to facilitate the installation of new wiring.
  • Plumbing installation and rooftop exhaust duct installation continued. The roofing pull test took place, as well as the installation of scaffolding in the stair tower at the loading dock.
  • Epoxy floor demolition continued in the kitchen, as well as mechanical equipment installation.

Week of July 10th

  • Exterior work will be ongoing along with the second stockpile.
  • Sheetrock wall installation will continue along with the first coat of paint in many areas.
  • Containment and abatement of room 122 will take place.
  • Kitchen floor removal will continue.
  • Electrical coring and rough-in for the kitchen equipment will take place.
  • Lighting and roof exhaust installation continues.

View all posts