West Campus Dining Expansion – Construction Update – 07/07/23
General Project Updates
- This past week, exterior work began and excavation of the site’s utilities and stockpiling soil took place.
- Soffit framing and drywall installation continued. The framing inspection was approved Wednesday.
- Electrical installation was completed and the old lights were swapped out.
- The KDP and KP3 panels were shut down to facilitate the installation of new wiring.
- Plumbing installation and rooftop exhaust duct installation continued. The roofing pull test took place, as well as the installation of scaffolding in the stair tower at the loading dock.
- Epoxy floor demolition continued in the kitchen, as well as mechanical equipment installation.
Week of July 10th
- Exterior work will be ongoing along with the second stockpile.
- Sheetrock wall installation will continue along with the first coat of paint in many areas.
- Containment and abatement of room 122 will take place.
- Kitchen floor removal will continue.
- Electrical coring and rough-in for the kitchen equipment will take place.
- Lighting and roof exhaust installation continues.