West Campus Dining Expansion – Construction Update – 06/23/23
General Project Updates
- Work is ongoing for the West Campus Dining Expansion and repairs to the West Campus steam line were started.
- A large portion of the West Campus Plaza has been fenced off to accommodate both the steam line repair project and the West Campus Dining Expansion project.
- Pedestrian traffic from Agganis Way through the Plaza is still permissible with police details on site to direct pedestrian traffic as needed.
- Work for the Residence Life Office is substantially complete, pending new furniture and some minor punch list items.
- Work to renovate the Dining Hall is underway with the floor demolition complete, new partitions for the additional dining area and gluten-free concept are underway, floor preparation in the back-of-house kitchen is in progress. Rough plumbing, electrical and mechanical installations are ongoing.
Week of June 26th
- Work this week includes the installation of flooring in the back-of-house kitchen, light installations in the dining hall, sheetrock installations at the new walls throughout, ceramic flooring in the servery area, and extensive landscaping work in the plaza area.
- There could be impacts to pedestrian traffic in and around Claflin Hall as site work continues. Police Details will be on site to detour traffic as required.