West Campus Dining Expansion – Construction Update – 05/26/23
General Project Updates
- The Residence Life Offices moved from their temporary space into their newly renovated office space. While there are still some punch list items remaining, the space is substantially complete.
- With the completion of the Residence Life Offices, work began on the project’s second phase: the renovations to the West Campus Dining Hall. This included temporary protections going in, temporary partitions being put up, demolition, disconnecting and make-safe of appliances, and the demolition of the old security desk.
- Exterior work to the existing drain lines was completed.
Week of May 29th
- Demolition continues, metal stud framing begins, and ongoing work on the Phase 1 punch list continues.
- Dumpster exchange in the plaza will take place at least every other day, sometimes daily.
- Exterior site work will be laid out.
- Kitchen equipment will be moved, mechanical equipment will be made safe and disconnected, and the fire sprinklers will be turned up.