West Campus Dining Expansion – Construction Update – 05/19/23
General Project Updates
- In the Residence Life Offices, ceiling tile work was completed, doors installed, electrical work completed, and millwork installed.
- In the new corridor, ceiling tiles were installed, the grease trap work was completed and work on the exterior canopy continued.
Week of May 22nd
- The Residence Life Office will be substantially completed this week. The Residence Life staff will be returning to their offices this week.
- Phase 2 work in the dining hall and kitchen areas will begin, including the construction of temporary partitions and miscellaneous make-safe efforts to prepare for floor demolition, lighting replacement, and the construction of the new gluten-free kitchen area, along with the demo of the existing security station.
- On Monday, 5/22, the electrical contractor to mobilize to the job site. The dumpster, scissor lift, and temporary toilets will be delivered.
- On Tuesday, 5/23, and Wednesday, 5/24, light fixtures will be delivered, and the storm drain camera investigation at the manholes in the plaza and Nickerson Field will take place.
- Dumpster exchange will take place at the end of the week.