West Campus Dining Expansion – Construction Update – 5/12/23
General Project Updates
- Corridor flooring, office carpeting, sheetrock patching and painting, installation of vestibule storefronts, and electrical and data installations have been completed.
- On the exterior of the building, the team worked on site clean-up for Commencement Weekend, painting the temporary door, roofing at the canopy, re-location of temp fencing, and removal of the dumpster.
Weekend of May 13th
- Movers will remove all the tables and chairs from the dining hall to allow for Commencement-related activities to be set up.
Week of May 15th
- Installation of the walk-off mat at the vestibule continues.
- Installation of the ceiling tiles throughout the space is underway.
- Installation of the temporary wall and door at Residence Life offices continues.
- The final painting of walls and ceilings will be completed.
- Doors and hardware will be installed.
- Roof work at the canopy will continue on Monday and Tuesday.
- By the end of this week, the Residence Life Offices will be substantially complete and preparation for Phase 2 (dining hall renovations) will begin. This work consists of pre-construction layouts and investigations, as well as coordination meetings with various subcontractors.