West Campus Dining Expansion – Construction Update – 5/12/23

General Project Updates

  • Corridor flooring, office carpeting, sheetrock patching and painting, installation of vestibule storefronts, and electrical and data installations have been completed.
  • On the exterior of the building, the team worked on site clean-up for Commencement Weekend, painting the temporary door, roofing at the canopy, re-location of temp fencing, and removal of the dumpster.

Weekend of May 13th

  • Movers will remove all the tables and chairs from the dining hall to allow for Commencement-related activities to be set up.

Week of May 15th

  • Installation of the walk-off mat at the vestibule continues.
  • Installation of the ceiling tiles throughout the space is underway.
  • Installation of the temporary wall and door at Residence Life offices continues.
  • The final painting of walls and ceilings will be completed.
  • Doors and hardware will be installed.
  • Roof work at the canopy will continue on Monday and Tuesday.
  • By the end of this week, the Residence Life Offices will be substantially complete and preparation for Phase 2 (dining hall renovations) will begin. This work consists of pre-construction layouts and investigations, as well as coordination meetings with various subcontractors.

View all posts