West Campus Dining Expansion – Construction Update – 4/14/23

Project Updates

  • The drywall installation in the Residence Life offices is expected to be completed this Saturday, 4/15.
  • The electrical cabling above the ceiling is about 75% complete, and the HVAC ductwork installation is about 90% complete.
  • The exterior concrete and brick wall removal at the new building entrance was completed. This area has been temporarily infilled with plywood until the new storefront arrives and is installed.
  • The rooftop condensing unit and electrical systems have been installed.
  • Repairs to the brick façade at the new entrance have begun and will continue into next week.

Week of April 17th

  • The walls in the Residence Life offices will be primed and receive their first coat of paint. The flooring installation will also begin this week.
  • Rough electrical work above the ceiling will continue.
  • The acoustic ceiling tile grid will be installed later in the week.
  • Work on the exterior brick façade will continue.
  • A flooring material delivery is scheduled for Tuesday, 4/18.