During the weekend of January 21st

  • On Saturday and Sunday, crews will be on site delivering and assembling furniture.
  • Also on Saturday, crews will be on site completing painting and millwork punch list items.

During the week of January 23rd

  • Deliveries and assembly of furniture will continue.
  • Crews will continue addressing punch list items throughout.
  • Start-up, testing, and commissioning of the building’s systems continues.
  • Installation of AV equipment in the classrooms and conference rooms will continue.
  • Exterior site work continues in the laneway between the building and the Bay State Road brownstones and at the Granby Street/Bay State Road park.
  • Assembly of the bike shelter between the building and Sargent College continues.