Center for Computing & Data Sciences – Construction Update – 1/6/23
During the weekend of January 7th
- On Saturday, crews will be on site delivering and assembling furniture.
- Crews will also be continuing to paint the atrium stair and connect data wiring.
During the week of January 9th
- Crews will continue addressing punch list items and installing furniture throughout the building.
- Start-up, testing, and commissioning of the building’s systems continues.
- Installation of A/V equipment in the classrooms and conference rooms will continue.
- Exterior site work continues. Crews will begin installing granite pavers at the Granby Street and Bay State Road park.
- Assembly of the bike shelter located between the building and Sargent College will continue.
- Deliveries and assembly of office furniture will continue.