Kilachand Hall Phase 2 – Construction Update – 12/16/22
General Project Information
Kilachand Hall site plan during the course of construction.
Daily Work Hours from 8 am-4 pm. (Quiet study and exam period)
The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place.
Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road).
Jersey barrier site containment in place, pedestrian walkway also in place and operational. City sidewalk in front of Kilachand Hall is permitted to be used as part of the construction site limits.
Bike lane is fully functional in front of Kilachand Hall
BU parking spots directly behind Kilachand Hall on Back Street remain a “no parking zone”. This will continue for the duration of the project to maintain an adequate drive lane for local traffic on Back Street and allowing for the construction team to safely contain a work area north of the dormitory
Steel erection on level 9.
During the week of December 19th
The construction team acknowledges the quiet study and exam period from 12/12 through 12/22. Work on site has been scaled back to only critical schedule items we feel are not going to be disruptive to the students.
Empire Masonry crew starting elevator shaft construction on level 9.
Royal Steam Plumbing and Murphy Electric to continue with scheduled critical rough in work in the new suite areas.
Mass Acoustics will have a carpenter on site to handle any miscellaneous framing needed in the renovation areas.
Access to scaffold stair towers will be limited to only the west side stair tower outside of the unoccupied construction area.
Consigli/Riggs team on site for cleaning support and supervision.