During the weekend of December 3rd
On Saturday, crews will continue the installation of the finishes around the atrium’s monumental stair on the interior of the building. Installation of ceiling systems will continue in the corridors of the tower. Final coat of paint and touchups continue. Startup, testing, and commissioning of the building mechanical systems continue.
On the exterior of the building, installation of landscape site features, curbing, and sidewalks continue.
On Sunday, crews will return to the site to continue to install finishes in high-traffic areas, such as the ground floor, elevator lobbies, and stairways.
Deliveries for miscellaneous materials will also occur throughout the day.
Installing landscape pavers at the plaza.
During the week of December 5th
Crews continue installing finish material for the stair guardrails at the atrium stair.
Installation of finishes will continue throughout, including whiteboards, corner guards, cabinetry, wood and acoustical ceilings, and final paint.
On the terraces, final details are being installed with final plantings, lighting, and security bollards ongoing.
On the 17th floor, crews will continue installing the modular partition, lighting, and finish wall panels.
Start-up, testing, and commissioning of the building’s systems continues.
Exterior site work continues with the retaining wall, ramp, stair, planter, and tree installation at the laneway between the building and the rear of the Bay State Road brownstones.
Deliveries and assembly of office furniture will continue, working up the building.
The project will continue utilizing a second shift, from 3 pm to 11 pm, Monday through Friday to advance interior work, accommodate off-hour deliveries, material loading, and debris removal. Select subcontractors may continue working on the third shift, from 11 pm to 7 am, to advance the start-up and testing of building systems while the workforce is less than during normal business hours.
Please be aware in addition to daily deliveries, trucks with large trailers will be staged adjacent to and moving around the site. Pedestrians should be aware of all safety and directional signage in the areas as pedestrian and vehicle travel paths may be altered.