Kilachand Hall Phase 2 – Construction Update – 05/13/22

Week of 5-16 scaffolding erection locations.

During the week of May 16th

  • Scaffold erection will continue with the east side elevation in the alley and the south side elevations both east and west of front entrance.
  • Scrim (mesh protection) installation will start on the west side scaffolding.
Scaffold erection on the south and east side.

General Project Information

  • Daily work hours are from 7 am – 3:30 pm through May 21st.
  • Starting in early April, and continuing through the weeks leading up to Commencement, there will be some light construction enabling activity consisting of scaffold erection in select areas around Kilachand Hall.
    • The erection of the scaffolding will take approximately 2 weeks in each location.
    • Once completed, that section will be locked out and no further activity will take place until after commencement.
Scrim installation to start on west and south elevations.