Kilachand Hall Phase 2 – Construction Update – 05/06/22
During the week of May 9th
No work will take place this week due to the quiet study and exam period.
Work will commence at 9 am on Monday, May 16th.
Concrete footing and piers placed for man and material hoist.
General Project Information
Daily work hours are from 9 am – 4:45 pm through May 21st.
Starting in early April, and continuing through the weeks leading up to Commencement, there will be some light construction enabling activity consisting of scaffold erection in select areas around Kilachand Hall.
The erection of the scaffolding will take approximately 2 weeks in each location.
Once completed, that section will be locked out and no further activity will take place until after commencement.
From May 5th through May 13th, through the study and exam periods, no construction enabling activity will take place at all to adhere to the quiet time on campus.