During the weekend of April 9th
On Saturday, installation of the atrium’s monumental stair will continue. Framing, hanging, and finishing drywall will continue in the tower. Crews will also be on site assembling and installing curtain wall panels. Installation of the building’s roofing system will continue. Workers will continue applying fireproofing materials to the building’s steel beams and columns.
Crews will be on site Sunday to advance the installation of the terrace roofing systems.
Installing the curtain wall at the 17th-floor event space.
During the week of April 11th
Installation of curtain wall panels at the tower will continue on the 18th and 19th floors. Delivery and assembly of the panels before installation will continue.
Installation of finishes will continue in the sub-basement and lower level with rubber and tile flooring going in, framing of ceilings, installing the raised flooring system in the classrooms, and painting throughout.
On floors 2 through 5, crews will continue finishing walls, polishing concrete floors, and framing ceilings.
On floors 6 through 12, framing walls and hanging drywall is underway.
On the 13th floor, crews will be applying an intumescent coating to the steel columns.
On floors 14 through 17, the MEP subcontractors will continue with system rough in, installing electrical conduit, hangers, and piping.
In the mechanical spaces on the 18th and 19th floors, crews will continue installing piping, ductwork, conduit, and wires to the mechanical equipment.
Installation of the atrium’s monumental stairs will continue. The focus this week will be on the section connecting the third and fourth floors.
The elevator subcontractor will continue the installation of elevators 7 and 8 in the podium and begin the buildout of elevators 1, 2, and 3 on the north side of the tower’s core.
Installation of the roofing system at the terraces will continue.
Crews will continue working from the elevated deck to construct the soffit at the underside of the 10th floor along Commonwealth Avenue and the underside of the 12th floor along Granby Street.
At the former park at the corner of Bay State Road and Granby Street, crews will continue excavation and installation of the storm drainage and geothermal systems.
Trucking activity to and from the site will be occurring daily with trucks entering and exiting the designated gates.
Installing tile wall finish in podium’s 3rd-floor bathroom.