Center for Computing & Data Sciences – Construction Update – 02/04/22
During the weekend of February 5th
On Saturday, crews will be on site to continue buildout of elevators 4, 5, and 6. In the tower core, installation of mechanical, plumbing, and fire protection rough will continue. Crews will be on site assembling and installing curtain wall panels. Installation of the monumental stair will continue. Installation of the roofing system will also continue; this activity is weather dependent.
Installing curtain wall panels for the tower’s 9th floor.
During the week of February 7th
Installation of curtain wall panels at the tower will continue on the 9th and 10th floors. Delivery and assembly of the panels before installation will continue on the floors above.
In the subbasement and lower level, wall finishing is ongoing while crews from the mechanical, electrical, and plumbing (MEP) subcontractors continue installing their respective systems.
On floors 2 through 6, wall framing, overhead MEP rough install continues, as well as hanging drywall.
On floors 9 through 17 of the tower, MEP subcontractors will continue with system rough install and installing electrical conduit, hangers, and piping. Wall framing will occur in select areas.
On the 7th and 8th floors, crews will be applying an intumescent coating to the steel columns.
Installation of the atrium’s monumental stairs will continue.
The elevator subcontractor will continue installing cab shells and wiring for elevators 4, 5, and 6 in the tower while beginning the buildout of the shafts for elevators 7 and 8 in the podium.
Installation of the roofing system at the podium will continue as weather allows.
In the mechanical spaces on the 18th and 19th floors, crews will continue installing piping, ductwork, conduit, and wires to the mechanical equipment.
Within the alleyway, the site contractor will continue trenching, and installing piping to connect the individual geothermal well circuits before connecting to the building.
Trucking activity to and from the site will be occurring daily with trucks entering and exiting the designated gates.
Installation of mechanical, electrical, and plumbing rough ongoing on the podium’s 3rd floor.