Center for Computing & Data Sciences – Construction Update – 3/12/21
Rebar installed in advance of the concrete placement for the tower’s lower level slab
During the weekend of March 13th
Crews intend to work on site Saturday to continue to advance progress on the 8th floor of the tower’s core.
During the week of March 15th
At the tower’s core, concrete is scheduled to be placed for the 8th floor early in the week. The remaining of the week will be spent removing the formwork from the 8th floor and installing formwork and rebar at the 9th.
Crews will continue with the installation of rebar and formwork for the remaining section of the tower’s foundation wall at the transition between the tower and the podium.
The installation of waterproofing at the tower’s foundation walls will continue. The backfilling of these areas will follow as waterproofing is completed.
In the podium’s basement, installation of metal decking for the top of the duct tunnel will continue, while the installation of under slab conduit and piping progresses.
Crews will begin loading and spreading crushed stone to the basement of the podium and the lower level of the tower, which will serve as a subgrade material for the finish slabs.
Please be aware of all directional signage, as pedestrian travel paths may be altered. We will continue to provide you with up-to-date information via these notifications.
Final details coming together prior to concrete placement of the core’s 7th floor