Center for Computing & Data Sciences – Construction Update – 2/5/21
Hoisting core interior formwork panels into place
During the weekend of February 6th
Crews will be on site Saturday to continue to install rebar and formwork for the tower’s core.
During the week of February 8th
Installation of rebar and formwork will begin next to Sargent College for the bike shelter foundation.
Following the completion of the concrete work for the below-slab duct tunnel, crews will begin installing the ductwork.
Rebar and formwork installation will continue at the tower’s north foundation wall and core. Concrete has been placed to the 2nd floor; rebar installation is now underway for the 3rd floor with concrete scheduled to be placed mid-week.
Please be aware of all directional signage, as pedestrian travel paths may be altered. We will continue to provide you with up-to-date information via these notifications.
Installation of rebar at the tower’s north foundation wallFinal section of the tower’s south foundation wall was completed this week