Center for Computing & Data Sciences – Construction Update – 2/5/21

Hoisting core interior formwork panels into place

During the weekend of February 6th

  • Crews will be on site Saturday to continue to install rebar and formwork for the tower’s core.

During the week of February 8th

  • Installation of rebar and formwork will begin next to Sargent College for the bike shelter foundation.
  • Following the completion of the concrete work for the below-slab duct tunnel, crews will begin installing the ductwork.
  • Rebar and formwork installation will continue at the tower’s north foundation wall and core. Concrete has been placed to the 2nd floor; rebar installation is now underway for the 3rd floor with concrete scheduled to be placed mid-week.
  • Please be aware of all directional signage, as pedestrian travel paths may be altered. We will continue to provide you with up-to-date information via these notifications.
Installation of rebar at the tower’s north foundation wall
Final section of the tower’s south foundation wall was completed this week