During the weekend of September 5th
- On Saturday, crews will be on site to continue with the installation of cross bracing for the support of the excavation system.
- Drilling of the inclinometer at the north edge of the tower will continue.
During the week of September 7th
- Due to the Labor Day holiday, there will be no work on site on Monday.
- Excavation for the building foundations continues, working from west to east across the site.
- Installation of cross bracing members for the support of excavation system continue in the tower portion of the building.
- A concrete “mud mat” will be poured at the bottom of the excavation in the podium. This will act as a working and building surface for the rest of the building’s foundation system.
- A waterproofing membrane will be installed beginning in the podium.
- Horizontal piping will be installed connecting the individual geo-thermal wells that were drilled last summer.
- Mobilization for the tower crane assembly will begin on Friday and will continue throughout the weekend. For additional information regarding this activity, please follow the link below.
- As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.
- We will continue to provide you with up to date information via these notifications.
Tower crane assembly is scheduled for September 11 – September 13.
- For additional information on the upcoming activity, please visit Tower Crane Narrative to Community.