Center for Computing & Data Sciences – Construction Update – 6/19/20

During the week of June 22nd

  • Installation of utility feeds from Granby St. to the site will continue.
  • Driving of the sheeting for the Support Of Excavation (SOE) system will continue. The project team will monitor and communicate. The construction manager has indicated that the installation at the east end of the site (closest to Sargent), working towards Commonwealth Avenue will begin.
  • At the mock-up (766 Commonwealth Avenue parking lot), installation of the façade panels will continue, and preparations will begin to install various masonry products.
  • As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up-to-date information via these notifications.
Set up of the temporary pedestrian sidewalk continues
Glass and façade panels installed at the mock-up