Center for Computing & Data Sciences – Construction Update – 5/15/20

During the week of May 18th

  • Crews will continue with the surcharge work, involving laying gravel material in the alley between the Granby St. lot and the Bay State Rd. brownstones.
  • Excavation within the perimeter of the site for installation of the support of excavation system will begin.
  • A concrete pad was poured at the 766 Commonwealth Ave. parking lot, this pad will serve as the foundation for a building mockup where the proposed façade materials will be assembled for review by Boston University and City of Boston officials.
  • As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up to date information via these notifications.
Continued dumping, spreading, and compacting of surcharge materials
Concrete foundation pad placed for the building mock-up