During the week of April 6th

  • On March 16, 2020, Boston Mayor Marty Walsh ordered the suspension of all construction projects as a result of the Coronavirus pandemic (“COVID-19”). Due to this direction, construction activity has been suspended permission is granted to resume.
  • The project team continues working remotely to advance project planning efforts.
  • Personal from the project team will be onsite from time to time for safety and security checks.
  • Due to the moratorium on construction in the City of Boston for the foreseeable future, we will forego weekly updates until Boston Mayor Walsh lifts this suspension.
Soil surcharge materials in the alley
Soil surcharge materials in the alley