Geothermal Well Drilling Initiative – Construction Update – 1/24/20

During the week of January 27th

Parking Lot N

  • The drilling subcontractor will continue installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N.
  • The drilling subcontractor will be pressure testing the piping within the completed boreholes.

Alleyway

  • The drilling subcontractor will be pressure testing and flow testing the piping within the completed boreholes.

Park

  • Construction equipment will be making periodic trips into the fenced area of the park to access the stockpiled materials.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!

High-performance geothermal exchange vertical piping installation in parking lot
High-performance geothermal exchange vertical piping installation in parking lot

View all posts