Geothermal Well Drilling Initiative – Construction Update – 1/17/20
During the week of January 20th
Parking Lot N
- The drilling subcontractor will continue installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N.
- The site subcontractor will be installing precast concrete structures over the piping.
Alleyway
- Construction equipment will be making periodic trips into the fenced area of the alleyway to access the stockpiled materials.
Park
- Construction equipment will be making periodic trips into the fenced area of the park to access the stockpiled materials.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!