BU Children’s Center – Construction Update – 1/16/20
During the week of January 13th
On site, work includes excavating for and installing the stormwater infiltration system.
Main Building
- Insulating of HVAC piping will occur on the 3rd floor.
- Installation of lights will occur on the 3rd floor.
- Boiler plumbing work will occur in the basement.
- Fire protection work will occur in ceilings.
- Installation of window frames and windows will occur.
- Door, frames, hardware, and millwork installation will occur on the first and second floors.
Connector
- Connector building will receive cedar siding.
- Installation of window frames will occur.
- Mechanical, electrical, and plumbing installation and insulation will occur along with fire protection.
During the week of January 20th
On site, work will include excavating for and installing the stormwater infiltration system. Rough grading of exterior playground will occur.
Main Building
- Insulation of HVAC piping will occur on the 3rd floor.
- Fire protection work will occur in ceilings.
- Installation of ceiling tiles will occur.
- Door, frames, hardware, and millwork installation will occur on the first and second floors.
Connector
- Connector building will receive cedar siding.
- Installation of windows will occur.
- Mechanical, electrical, and plumbing installation and insulation will occur along with fire protection.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!