Howard Thurman Center – Construction Update – 11/08/19

Week of November 11, 2019

General:

Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking garage and up through the fifth floor is primary means of access. The existing elevator will continue to remain functional throughout the entirety of the project. All stairwells are available for emergency egress. Temporary emergency egress signs are posted throughout.

Garage Level

  • Miscellaneous mechanical, electrical, and plumbing will continue.
  • The installation of both the passenger and the HTC elevators will continue.
  • Removal of temporary fencing to continue.
  • Insulation of mechanical duct and piping will continue.

On the 1st Level

  • Installation of millwork will continue.
  • Installation of vestibule ceiling will continue.
  • Installation of interior doors and hardware will continue.
  • Installation of drywall at the west vestibule entrance will commence.
  • Grinding and floor prep of the public corridor floors will continue.
  • Painting of the ornamental ceiling and miscellaneous area will continue.
  • Air-handler balancing and testing will continue.
  • Miscellaneous HVAC and mechanical is ongoing.
  • Ongoing installation of light fixtures.
  • HTC stair trim installation will continue.

On the Mezzanine Level

  • MEP punch-list is ongoing.

On the 2nd Level

  • Temporary directional signage is placed to help the public navigate.
  • Grinding of the HTC flooring is ongoing.
  • Painting touchup in both the common areas, as well as construction, will continue.
  • Installation of interior doors and hardware will continue.
  • Installation of millwork will continue.
  • MEP finish work is ongoing.

On Levels 3, 4, and 5

  • Installation of the fire alarm system will continue.
  • The passenger elevator installation is ongoing.
  • Framing of elevator vestibules will continue.
  • MEP punch-list.

Exterior

  • Caulking and sealant of windows will continue.
  • Installation of the arcade pavers will continue.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!

HTC stair trim being installed

 

Ongoing painting of new corridor
Installation of tracks for millwork being installed in the event space