Geothermal Well Drilling Initiative – Construction Update – 7/19/19

During the week of July 22nd

Parking lot N

  •  Pending disposal facility approvals, the subcontractor will continue to stockpile soil materials within the fenced in areas prior to testing and removal from the site.
  • Construction equipment will be making multiple trips from the alley to the parking lot N storage area.
  • Pending confirmation from the subcontractor, tree removals along the north edge of parking lot N are anticipated towards the end of the week. Parking spaces along the north edge of the lot will be impacted temporarily.

Alleyway

  •  The drilling subcontractor anticipates completing drilling at GT-11. Upon completion, drilling will begin at GT-10, further to the west behind Sargent College.
  • A second drill rig will continue to drill and set the steel casing to the bedrock along the north side of the alleyway.

Park

  • The subcontractor completed drilling and verticality testing at GT-27. The high performance geothermal exchange piping installation started on 7/19 and will continue into Monday. Installation will be followed by pressure testing, capping, and manhole cover installation.
  • Construction equipment will be making multiple trips into the park to access the stockpiled materials.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!

Drilling and Casing operation at alleyway
Drilling and casing operation at alleyway
Drill Rig at GT-11
Drill Rig at GT-11v
High Performance Geothermal Exchange Piping install at GT-27
High Performance Geothermal Exchange Piping install at GT-27