During the Week of June 24

  • Demolition
    • Demo 3-car garage
  • Site
    • Installation of sewer line to play support building
  • Concrete
    • Layout for elevator at main building
  • Rough Carpentry
    • Structural framing work at main building
  • Window Restoration
    • Strip lead paint at window openings

 

    During the Week of July 1

    • Site
      • Installation of sewer line to play support building
      • Back fill 3-car garage foundation and prep for footings
    • Concrete
      • Form and pour elevator pit footings and walls
    • Rough Carpentry
      • Structural framing work at main building
    • Window Restoration
      • Strip lead paint at window openings