BU Children’s Center – Construction Update – 6/21/19
During the Week of June 24
- Demolition
- Demo 3-car garage
- Site
- Installation of sewer line to play support building
- Concrete
- Layout for elevator at main building
- Rough Carpentry
- Structural framing work at main building
- Window Restoration
- Strip lead paint at window openings
During the Week of July 1
- Site
- Installation of sewer line to play support building
- Back fill 3-car garage foundation and prep for footings
- Concrete
- Form and pour elevator pit footings and walls
- Rough Carpentry
- Structural framing work at main building
- Window Restoration
- Strip lead paint at window openings
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!