Geothermal Well Drilling Initiative – Construction Update – 5/10/19

During the week of May 13th

Park Test Well #3

• The site subcontractor has removed fencing, restored the grading, and re-installed the park specialties. BU’s Grounds team will follow-up installing mulch ahead of Commencement weekend.

• No work is scheduled for test well #3 until after commencement.

Alley

• Temporary fencing and stockpiled drilling materials have been removed from behind Sargent College.

• No work is scheduled for the alley until after commencement.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!

Grading restoration underway at Granby Park
Grading restoration underway at Granby Park

View all posts