During the week of March 18:

Parking Lot Test Well #1

  • Fencing will be removed, and the parking areas will be returned to BU.

Alley Test Well #2

  • Fencing has been removed at the test well location and relocated to create a storage area along the retaining wall for piping, park amenities, ect.

Park Test Well #3

  • Fencing has been installed around the park area and equipment will be mobilizing to the site on 3/15 and 3/18.
  • This week, starting on 3/18, the drilling contractor anticipates delivery of drill rods on 3/22 and will be beginning set the steel pipe casing for geothermal test well #3. A water tank truck will periodically be crossing Granby St to access the hydrant on Bay State Rd.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!